Artemis Astronauts
GAO

Full report

NASA is embarking on a series of missions—collectively known as Artemis—that will return astronauts to the moon and ultimately bring humans to Mars over the next decade-plus.

The guidance NASA uses to create and manage Artemis mission schedules was intended for individual programs, not missions. Missions integrate several programs together and require coordination across different NASA divisions and with contractors. Schedule guidance specifically for missions would help NASA coordinate integration activities, as Artemis missions will involve more programs over time.

Our recommendations include creating mission schedule guidance.

What GAO Found

The National Aeronautics and Space Administration (NASA) plans to conduct Artemis missions—a series of missions that will return astronauts to the moon, build a sustainable lunar presence, and ultimately bring humans to Mars—into the 2030s.

Artemis Missions and the Number of Programs Needed for Each Mission

To do this, NASA will need to develop, acquire, and integrate a number of new systems. NASA has made progress on integration and risk management for the first lunar landing mission, Artemis III. For example, NASA established integration processes, roles, and responsibilities, and recently took additional steps to manage risks for the series of missions.

NASA, however, does not yet have guidance for creating or managing Artemis mission schedules that will help integrate the individual programs required for launch. NASA is using existing schedule management guidance developed for individual programs, not multi-program missions. Without guidance specifically for multi-program missions, NASA lacks reasonable assurance it has consistent schedule management practices in place for the Artemis schedules. Schedule management guidance would also assist coordination, which will be increasingly necessary as the Artemis missions will involve more programs over time and therefore become more complex.

NASA conducts workforce planning through the programs that comprise the Artemis missions across the next 5 budget years. NASA faces uncertainties beyond that horizon that have hindered longer-term planning. However, NASA is committing billions of dollars in development and production contracts for future Artemis missions that extend into the 2030s. This will require an extensive workforce to execute. Prior GAO work found that other agencies facing uncertainty assessed a range of future options, known as scenario planning, which provided flexibility to determine future workforce needs. In May 2022, NASA officials said they were examining the use of scenario planning to help future workforce planning efforts. But they have not yet completed or implemented guidance to do so. As NASA begins to execute the first of many Artemis missions, it has the opportunity to use scenario planning to inform future workforce environments it may face and address broader workforce challenges.

Why GAO Did This Study

In May 2021, GAO found that NASA faced many challenges to its ambitious goal of returning astronauts to the moon by 2024. Subsequently, NASA delayed the planned lunar landing, known as Artemis III, to no earlier than 2025. Artemis III is one in a planned series of missions to eventually establish a sustainable lunar presence and a path to Mars over the next decade-plus. Successfully executing these missions requires extensive coordination across several NASA programs and with a wide range of contractors to ensure systems operate together seamlessly and safely.

A House report to an appropriations bill included a provision for GAO to review NASA’s proposed lunar-focused programs. This report assesses the extent to which NASA (1) is managing mission integration risks; (2) developed Artemis mission-level schedules; and (3) assessed the ability of the Artemis workforce to manage and oversee lunar landing missions.

GAO reviewed relevant NASA documents, schedules, and plans and interviewed NASA headquarters and center officials.

Recommendations

GAO is making four recommendations, including that NASA develop Artemis mission-level schedule management guidance and develop guidance on conducting Artemis workforce scenario planning. NASA concurred with all four of the recommendations.

  • The NASA Administrator should ensure that the Chief Financial Officer, in coordination with the mission directorates, develops Artemis mission-level schedule management guidance.
  • The NASA Administrator, in coordination with the relevant mission directorates, should ensure that NASA conducts a schedule risk analysis for the Artemis II mission as close as possible to completion of the Artemis I mission and update it as needed to incorporate schedule updates and new risks.
  • The NASA Administrator, in coordination with the relevant mission directorates for Artemis III and later missions, should ensure that NASA develops guidance for division-level schedule collaboration including setting expectations for data sharing and the type(s) of data required.
  • The NASA Administrator should ensure that the Office of the Chief Human Capital Officer develops guidance that identifies a regular and recurring process for long-term Artemis workforce scenario planning to address future uncertainties, at least 5 years beyond the existing 5-year workforce plans.