USA SAFER Panel Meeting Minutes September 7, 2000

By SpaceRef Editor
September 7, 2000
Filed under

The SAFER Panel met at JSC on September 7, 2000 in Building 1 room 376G at 10:00 a.m.

Meeting participants:


Panel Chair XA/ Anh Huynh


Panel Secretary HSMS/ Theresa Elms


Panel Members CB/ Claude Nicollier


ER/ Kevin Lewis


EP/ Frank Davies


NC/ Ron Cook


NT/ Rafiq Hashmani


USA/ Armon Knight



The following items were discussed:

1. Flight Readiness


  • STS—106 (2A.2b) Manifest Support


No change.




  • STS—92 (3A) Manifest Support


The SAFER pre-ship functional checkouts are presently in work. The system leak check will begin on 09/11/00.

USA submitted a fitcheck plan for STS-92 (3A) on 09/07/00 (see file below).




  • STS—97 (4A) Manifest Support


ER/Kevin Lewis and USA/Armon Knight will develop a fit check plan for STS-97 (4A) once the fit checks for STS-92 have been completed.



2. FIAR/DR Closure Status


  • JSC-ER0027, Thruster Firing Failure at 150 deg. F (Open 143 days)


A draft closure for JSC-ER0027 has been prepared. JSC-ER0027 is scheduled to be closed after the SAFER —309 DCR on 09/08/00.



3. Configuration Control


  • Hardware/Software Configurations


No change.




  • CR Implementation


    • CR H-0670 R1, AAH LED Function Modification




The AAH LED function modification will be performed on SAFER unit SN 1007 after STS-106.





    • CR H-0683, On-Orbit Stowage Bag




NC/Ron Cook is continuing to research which requirements are applicable for the On-orbit Stowage Bag certification. After he completes his review he will discuss the results with EC/Gary Nickel.





    • CR H-0753 R1 Power Switch Guard Modification




Design concepts are still in work by ER.





    • CR H-0760 SAFER NBL & 1-G Hi-Fi Mockup Upgrades




HSMS/Anthony Hall provided the following SAFER NBL & 1-G Hi-Fi Mockup Upgrades Weekly Activity Report and Schedule Status (see files below):

 





    • CR H-0788, -305 SAFER Battery Design, Fabrication & Implementation

EP/Frank Davies presented the status of the —305 batteries for STS-92 (see file below).

 


    • CR H-0865, SAFER Thermal Enhancements

The DCR for the -309 SAFER is scheduled for 09/08/00, in building 32, room 146.


Proposed CR’s



    • CR H-0749 R1, SAFER On-Orbit Trainer


On hold until funds become available in the next fiscal year.



    • CR H-0806,-307 Rechargeable Battery CR





On hold pending funding from XA in the next fiscal year.




    • CR H-0843, Latch Redesign



On hold until hi-fi mockup latches can be replaced with flight-like latches.




    • Extension of HCM Deployment Actuator and the Manual Isolation Valve Actuator




CR draft in work.





    • IMS Labeling

CR draft in work.


    • On-Orbit Stowage Bag Modifications (Docking Loads)




DX/Kenny Vassigh has incorporated redlines from DX/Anh Huynh and NC/Ron Cook in the On-Orbit Stowage Bag Modifications CR (see file below).




  1. Issues

None.


5. Special Topics


STS-92 SAFER DTO 689


CB/C. Nicollier presented the DTO pass/fail criteria for the STS-92 DTO 689 to the panel (see file below).


  1. EHB Presentation

None.


  1. CCB Presentation

None.


  1. PRCB presentation

  2. None.

  3. Action Items


  • NC/Ron Cook will determine which SAFER configuration (if any) was certified for 100 missions.

 


Submitted by: Approved by:

(Original signed by) (Original signed by)


Theresa M. Elms Anh H. Huynh


SAFER Panel Secretary USA SAFER Panel Chairman

 


 


 


















































































































Item


Assignee


Description


Status


06-01


C. Price

 


 


 


 


 


 


 


 


 


J. Smith


Evaluate the MPLM environment for launch/landing of the USA SAFER.


06/25/99: Assigned.


07/29/99: In review by ER. ER as needed will request additional information.


08/05/99: ER needs information on directional G-loads during launch, landing, and emergency landing.


08/06/99: Additional MPLM information was provided by OM/E. Smistad.


08/11/99: ER will provide a cost and schedule estimate for the additional stress analysis.


08/26/99: ER estimated a cost of 32K and a schedule for 2 months. The task will be initiated by XA on 10/01/99 with FY00 funding.


10/28/99: Partial funding has been sent to ER on 10/21/99 & 10/29/99. ER to complete the evaluation with an ECD of 01/03/00.


12/02/99: ER will provide a new ECD due to time needed to turn the effort on through a task order.


01/06/00: ER provided a new ECD of 03/15/00.


03/30/00: ER has requested a new ECD from LM. New ECD of TBD.


04/06/00: The stress analysis is complete. The memo will be out soon, ECD 04/13/00.


04/20/00: ECD TBD.


05/04/00: The stress analysis is in the LM signature loop.


05/11/00: LM/James Shu presented the results of the MPLM stress analysis to the Panel. James Shu will provide ER with a memo summarizing the results. ER will forward the memo to XA. XA will discuss the angular acceleration topic with the MPLM group and ER will discuss with ES.


05/12/00: ES confirmed the need to include the angular acceleration in the analysis.


05/16/00: Awaiting MPLM contact person to be provided by XA I&O lead for 5A.1.


05/18/00: ER provided the analysis performed by LM.


05/25/00: ER is waiting for a response from the MPLM stress analyst. New ECD: TBD.


06/15/00: ER will meet with the MPLM contact person on 06/15/00.


06/22/00: The MPLM stress analysis is presently in review with the MPLM stress analyst.


07/13/00: The MPLM stress analyst (Satya Pilla) has provided additional MPLM launch/landing environment information. James Shu is reviewing the environment information.


07/20/00: The MPLM stress analyst has indicated that the SAFER can be launched in the MPLM. XA is waiting on the official confirmation from the MPLM group.


08/24/00: XA discussed the action with MPLM representative. New ECD 09/07/00.


07-04


K. Lewis


Provide a video recording of 1) NSI/Pyro Valve firing, 2) dry valve seating, 3) wet valve seating, 4) dry valve self-test, and 5) wet valve self-test.


06/25/99: Assigned as action 02-03 at the STS-96 USA SAFER IFA Investigation meeting.


07/09/99: Transfer action to USA SAFER Panel.


08/05/99: Recording completed except for NSI/Pyro Valve firing. ECD of TBD, pending available opportunity.


00-02-08


K. Lewis

 


 


 


 


 


 


 


A. Huynh


ER will initiate a stress analysis to determine how far the HCM deployment actuator and manual valve can be extended.


02/17/00: Assigned. ECD TBD.


02/24/00: EV/James Shu stated that the SAFER actuator supporting bracket needs to be changed if the actuator is extended.


05/04/00: The stress analysis is on hold while the small and x-large EMU managers perform SAFER reach evaluations with suited subjects to determine how far to extend the actuators. ECD: 05/19/00.


05/25/00: XA will initiate a CR for 2" extension to the actuators.


00-04-11


P. McCartney

K. Vassigh


Provide a video of the on-orbit trainer evaluation (SSC) as shown at the VRL and more technical information on the data rate specifications.


04/20/00: Assigned. ECD TBD.


06/15/00: DX will record on-orbit trainer evaluation (SSC) on video. ECD TBD.


00-05-06


K. Lewis


ER will determine the cost to build one more flight SAFER.


05/18/00: Assigned. ECD 06/16/00.


06/22/00: New ECD: TBD.


06/29/00: XA requests that ER look into getting a contractor to build another flight SAFER.


07/13/00: New ECD: 9/30/00.


00-05-07


K. Lewis

 


T. Elms



ER will investigate the problem with the weight relief lifting sling and the SAFER latches.


05/18/00: Assigned. ECD 06/01/00.


05/25/00: HSMS will verify that a comprehensive procedure is used to operate the weight relief lifting sling in order to prevent any damages to the SAFER latches.


06/15/00: New ECD 07/06/00.


07/06/00: HSMS determined that a comprehensive procedure to operate the weight relief lifting sling did not exist and that one needed to be written and released as a SSA Class III operational procedure. ECD 08/18/00.


07/13/00: HSMS has written a procedure detailing how to attach the SAFER to the EMU when using a weight relief lifting sling. The procedure is presently in review with Steve Anderson of the SSI group.


07/20/00: HSMS/T. Elms received comments to incorporate from ILC/Steve Anderson. Next the procedure needs to be reviewed by ER.


07/27/00: HSMS is searching for a picture showing the EMU/SAFER in the weight relief-lifting sling.


08/10/00: HSMS sent the procedure to ER/Kevin Lewis for review on 08/07/00.


08/17/00: HSMS will rewrite the procedure "real-time" as Gail Steel performs the steps on the engineering unit. New ECD: 8/31/00.


08/31/00: HSMS rewrote the procedure. Gail Steel reviewed and provided his inputs. The procedure is ready for release.


09/07/00: New ECD: 09/14/00.


00-06-01


K. Lewis


ER will provide DX with a video tape of the following operations for training:


  • Power switch guard installation & removal


  • Hand controller stowage


  • SAFER Checkout


  • SAFER Latch Operation (don/doff SAFER to PLSS; l use a USA/FCE

class III PLSS & SAFER engineering unit)


  • Inhibit Plug installation and removal


  • SAFER Battery Changeout

SAFER Transfer/Stow ops (both the launch/entry and on-orbit stowage bags from USA/FCE)



06/15/00: Assigned. ECD TBD.


07/13/00: DX and ER will develop a mutually agreed schedule to complete the activities.


08/31/00: New ECD: 09/05/00.


09/07/00: Activities were not performed on 09/05/00. New ECD: 09/11/00.


00-07-02


K. Lewis &


A. Knight


ER/Kevin Lewis and USA/Armon Knight need to develop a fitcheck plan for STS-92 (3A).


07/06/00: Assigned. ECD:07/20/00.


08/10/00: New ECD: 09/15/00.


09/07/00: USA submitted a fitcheck plan for STS-92 (3A) on 09/07/00. Closed.


00-07-05


M. Hembree


Investigate if the ERCM will be used in an EVA before the DTO, creating a glove cut hazard on the tether.


07/20/00: Assigned. ECD 08/10/00.


09/07/00: New ECD: TBD.


00-07-06


All


Submit any post-flight DTO questions for the STS-92 crew to DX/Mike Hembree.


07/20/00: Assigned. ECD 08/10/00.


09/07/00: New ECD: TBD.


00-07-07


D. Tani


C. Nicollier


Provide a consensus on DTO pass/fail criteria for STS-92 DTO 689.


07/20/00: Assigned. ECD 08/10/00.


08/17/00: New ECD: 08/31/00.


08/24/00: New ECD: 09/07/00.


09/07/00: CB/C. Nicollier presented the DTO pass/fail criteria for the STS-92 DTO 689 to the panel. Closed.


00-07-08


M. Hembree


Provide a DTO backup plan in case of RMS failure.


07/20/00: Assigned. ECD 08/10/00.


09/07/00: New ECD: TBD.


00-08-02


K. Lewis


Provide a formal memo to DX/Mary Fitts before STS-106 that gives the status for each SAFER unit.


08/03/00: Assigned. ECD TBD.


08/17/00: New ECD: 09/01/00.


08/31/00: ER sent a draft STS-106 memo to DX/Mary Fitts 08/31/00 which presented the status for each of the three SAFER units.


00-08-03


E. Darcy


Provide a work instruction for inspection of incoming electrical parts.


08/03/00: Assigned. ECD 09/11/00.


08/17/00: New ECD: 09/01/00.


09/07/00: New ECD: TBD.


00-08-04


E. Darcy


Contact Dave Homan or Jeff Hoblit/VRL to determine whether the battery simulation in the VRL is realistic.


08/03/00: Assigned. ECD 09/01/00.


08/17/00: New ECD: 08/25/00.


08/24/00: EP/Eric Darcy gave Jeff Hoblit instructions on how the VRL should be simulating the battery on 08/23/00. Jeff Hoblit will check his VRL algorithms against Eric’s instructions and report the results of the comparison. New ECD: 08/28/00.


08/31/00: Jeff Hoblit investigated how the VRL simulates the battery and is presently incorporating EP’s changes. New ECD: TBD.


09/07/00: Changes to the VRL battery simulation software are on hold while the configuration procedure is being determined.


00-08-06


K. Lewis


Provide a ROM on the following new latches:


1 — set of Class I tower latches


3 — sets of Class III tower latches



08/17/00: Assigned. ECD TBD.


09/07/00: New ECD: 09/14/00.


00-08-07


C. Mooty


Provide a ROM on the following new latches:


1 — set of Class I tower


3 — sets of Class III tower latches


08/17/00: Assigned. ECD TBD.


08/24/00: New ECD: 09/07/00.


08/31/00: New ECD: 09/28/00.


00-08-08


K. Lewis


A. Knight


ER/Kevin Lewis and USA/Armon Knight need to develop a fitcheck plan for STS-97 (4A).


08/24/00: Assigned. ECD 09/07/00.


09/07/00: A fitcheck plan for STS-97 (4A) will be determined after the fitchecks for STS-92 have been completed. New ECD: TBD.


00-08-09


T. Elms


K. Lewis


Prepare a configuration matrix for STS-106, STS-92 and STS-97 and document what the differences are between the configurations.


08/24/00: Assigned. ECD 08/31/00.


08/31/00: The configuration matrix was sent for ER’s review on 08/28/00. New ECD: 09/08/00.


09/07/00: New ECD: 09/14/00.


00-08-10


A. Knight


Determine if the SAFER units for 3A and 4A have been fit checked with a flight PLSS in the past.



08/31/00: Assigned. ECD 09/07/00.


09/07/00: New ECD: TBD.


00-09-01


R. Cook


NC/Ron Cook will determine which SAFER configuration (if any) was certified for 100 missions.


09/07/00: Assigned. ECD 09/14/00.