Status Report

Space Shuttle Status Report 25 September 2000

By SpaceRef Editor
September 25, 2000
Filed under

KENNEDY SPACE CENTER

SHUTTLE PROCESSING STATUS

KSC Contact: Joel Wells

Monday, Sept. 25, 2000
(4
p.m.)

NOTE: This is an orbiter processing report and does not necessarily reflect
the chronological order of upcoming Space Shuttle flights. Visit
http://www-pao.ksc.nasa.gov/kscpao/schedule/schedule.htm on the KSC Home
Page for the latest schedule of future Shuttle missions.

MISSION: STS-92 – 5th ISS Flight (3A) – Z-1 Truss, PMA-3

VEHICLE: Discovery/OV-103

LOCATION: Launch Pad 39A

TARGET KSC LAUNCH DATE/TIME: Oct. 5, 2000 at about 9:38 p.m. EDT

TARGET KSC LANDING DATE/TIME: Oct. 16, 2000 at about 5 p.m.

MISSION DURATION: 11 days

CREW: Duffy, Melroy, Wakata, Chiao, Wisoff, Lopez-Alegria, McArthur

ORBITAL ALTITUDE and INCLINATION: 177 nautical miles/51.6 degrees

Shuttle Processing Note: Prelaunch processing of Space Shuttle Discovery
continues at Launch Pad 39A toward a target launch date of Oct. 5. The
standard Helium Signature Test conducted last Friday indicated a small leak
in the orbiter’s main propulsion system. Shuttle engineers are developing a
troubleshooting plan to address the leak and expect no impact to the target
launch day. Over the weekend, workers successfully loaded Discovery’s
onboard propellant tanks.

Milestones:

Space Shuttle main engine flight readiness test begins – Sept. 25

Orbiter aft compartment close-outs begin – Sept. 26

Ordnance installation complete – Sept. 28

Flight Readiness Review – Sept. 28

Crew arrives at KSC – Oct. 1

Payload bay doors closed for flight – Oct. 2

MISSION: STS-97 – 6th ISS Flight (4A) – PV Module P6

VEHICLE: Endeavour/OV-105

LOCATION: OPF bay 2

TARGET KSC LAUNCH DATE/TIME: Nov. 30, 2000 at 10:48 p.m.

TARGET KSC LANDING DATE/TIME: Dec.10, 2000 at time TBD

MISSION DURATION: 10 days

CREW: Jett, Bloomfield, Tanner, Noriega, Garneau

ORBITAL ALTITUDE and INCLINATION: 177 nautical miles/51.6 degrees

Shuttle Processing Note: Technicians have completed orbiter camera alignment
and left-hand orbital maneuvering system leak checks. Following last week’s
main engine installation, workers are conducting engine interface leak
checks today. Engine heat shield installation continues to go well.
Functional tests of the orbiter’s external tank umbilical doors are in work
today.

MISSION: STS-98 – 7th ISS Flight (5A) – U.S. Laboratory

VEHICLE: Atlantis/OV-104

LOCATION: Orbiter Processing Facility (OPF) bay 3

TARGET KSC LAUNCH DATE/TIME: Jan.18, 2001 at 3:36 a.m. EDT

TARGET KSC LANDING DATE/TIME: Jan. 28, 2001

MISSION DURATION: 10 days

CREW: Cockrell, Polansky, Curbeam, Jones, Ivins

ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

Shuttle Processing Note: Workers completed post-flight orbiter power
validations on Friday. The payload bay doors were opened Saturday and
payload removal is planned for Tuesday. Technicians will begin main engine
removal later this week.

— end —

SpaceRef staff editor.