Status Report

Space Shuttle Status Report 20 Apr 2000

By SpaceRef Editor
April 20, 2000
Filed under

KENNEDY SPACE CENTER SPACE
SHUTTLE STATUS REPORT

THURSDAY, APRIL 20, 2000 (12:30 p.m. EDT)


MISSION: STS-101 — 3rd ISS Flight (2A.2a) – SPACEHAB DM

  • VEHICLE: Atlantis/OV-104
  • LOCATION: Launch Pad 39A
  • TARGET KSC LAUNCH DATE/TIME: April 24, 2000 at about 4:15 p.m.
  • TARGET KSC LANDING DATE/TIME: May 4, 2000 at about 12:42 p.m.
  • LAUNCH WINDOW: 5 minutes
  • MISSION DURATION: 9 days, 20 hours and 27 minutes
  • CREW: Halsell, Horowitz, Weber, Williams, Voss, Helms, Usachev
  • ORBITAL ALTITUDE and INCLINATION: 173 nautical miles/51.6 degrees

Shuttle Processing Note: Workers at Launch Pad 39A continue to process Shuttle Atlantis toward an April 24 launch date at about 4:15 p.m. Orbiter aft engine compartment close-outs are ongoing and should be complete tomorrow afternoon. External tank purge operations are in work today. Tomorrow, SPACEHAB late stow activities will occur.

The flight crew is slated to arrive at KSC’s Shuttle Landing Facility tomorrow at about 3 p.m. The STS-101 launch countdown begins tomorrow at 7 p.m. at the T-43 hour mark. Preliminary weather forecasts indicate generally favorable weather conditions for a launch on Monday.

Upcoming Milestones:
Flight crew arrival at KSC – April 21 at 3 p.m.
SPACEHAB late stow complete – April 21
Launch countdown begins – April 21 at 7 p.m.
Orbiter aft compartment close-outs complete – April 21

Information about the countdown and mission can be accessed electronically via the Internet at: http://www.ksc.nasa.gov/shuttle/countdown/ and at http://spaceflight.nasa.gov/

–end–

SpaceRef staff editor.