Space Shuttle Processing Status 29 May 2001

By SpaceRef Editor
May 29, 2001
Filed under , ,

MISSION: STS-104 – 10th ISS Flight (7A) – Airlock

VEHICLE: Atlantis/OV-104

LOCATION: Orbiter Processing Facility (OPF) bay 3

TARGET KSC LAUNCH DATE/TIME: NET June 20, 2001 at about 1:45 p.m.
EDT

TARGET KSC LANDING DATE/TIME: July 1, 2001

MISSION DURATION: 11 days

CREW: Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Over the weekend, workers completed tile drying and
waterproofing efforts on orbiter Atlantis and today began final preparations
to roll over to the Vehicle Assembly Building. Atlantis is expected to
begin moving toward the VAB transfer aisle between 3:30 p.m. and 4 p.m.
today. Managers continue to assess an STS-104 launch date of no earlier than
June 20.

Payload Processing Note: The U.S. Airlock is currently at the pad in the
payload changeout room. Minimal work will be conducted through the time the
orbiter arrives at the pad on June 3. The airlock will be installed into the
orbiter’s payload bay on June 6 and the payload bay doors will be closed for
flight June 14. The date for the crew’s Terminal Countdown Demonstration
Test is set for June 7-8.

MISSION: STS-105 – 11th ISS Flight (7A.1) – Leonardo MPLM

VEHICLE: Discovery/OV-103

LOCATION: OPF bay 2

TARGET KSC LAUNCH DATE/TIME: July 12, 2001 at 5:22 a.m. EDT

TARGET KSC LANDING DATE/TIME: July 23, 2001

MISSION DURATION: 11 days

CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov,
Turin; (ISS down) Usachev, Voss, Helms,

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Technicians have completed routine checks of
Discovery’s water spray boilers and landing gear. Main engine thrust vector
control testing is also complete. Aft compartment closeouts are in work
today.

Payload Processing Note: Experiment and supply rack installations continue
on the Leonardo Multi-Purpose Logistics Module (MPLM) in the Space Station
Processing Facility.

MISSION: STS-108 – 12th ISS Flight (UF1) -Raffaello MPLM

VEHICLE: Endeavour/OV-105

LOCATION: Orbiter Processing Facility bay 1

TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001

TARGET KSC LANDING DATE/TIME: Dec. 9, 2001

MISSION DURATION: 10 days

CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS
down) Culbertson, Dezhurov, Turin

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Endeavour’s three main engines were removed last
Thursday. Technicians are conducting routine inspections of the orbiter’s
reaction control system thrusters this week. Orbiter maneuvering system pod
checks are also under way.

MISSION: STS-109 – HST Servicing Mission 3B

VEHICLE: Columbia/OV-102

LOCATION: Vehicle Assembly Building high bay 4

TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002

TARGET KSC LANDING DATE/TIME: Jan. 28, 2002

MISSION DURATION: TBD

CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino

ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees

Shuttle Processing Note: Columbia will be transferred to Orbiter Processing
Facility bay 3 once Atlantis moves out. There, workers will begin
processing the orbiter for the STS-109 mission.