Space Shuttle Processing Status 27 Mar 2002

By SpaceRef Editor
March 27, 2002
Filed under , ,

MISSION: STS-110 – 13th ISS Flight (8A) – ITS S0 TRUSS AND MOBILE TRANSPORTER

VEHICLE: Atlantis/OV-104

KSC LAUNCH DATE: April 4, 2002

LAUNCH PERIOD: 2 – 6 p.m. EST

TARGET KSC LANDING DATE: April 15, 2002

MISSION DURATION: 11 days

CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Final processing operations continue on schedule with Shuttle Atlantis in preparation for the STS-110 launch to the International Space Station on April 4. Shuttle managers gave a go for the launch following yesterday’s comprehensive Flight Readiness Review. At Pad B, the S-Zero Integrated Truss Structure and Mobile Transporter will be installed in the orbiter payload bay today. Other work in progress includes integrity checks of the three EVA suits on board, aft closeouts and External Tank purge operations. The hot fire test of the replacement hydraulic power unit in the right aft Solid Rocket Booster was successfully completed yesterday.

SpaceRef staff editor.