Space Shuttle Processing Status 26 Aug 2002

By SpaceRef Editor
August 26, 2002
Filed under , ,

MISSION STS-112 — 15TH ISS FLIGHT (9A) – BA, ITS S1

VEHICLE: Atlantis/OV-104

TARGET LAUNCH DATE: Oct. 2, 2002 NET

TARGET LANDING DATE: Oct. 13, 2002

MISSION DURATION: 11 days

CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin

ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note: Nominal processing continues for Atlantis’ launch
to the International Space Station now scheduled for no earlier than Oct. 2.
Closeouts of the orbiter’s aft compartment are in work and Hydraulic/Flight
Control Checkout is scheduled for this week.
Engineering evaluation continues on the cracks found in the bearings located
in the JEL (jacking, equalization and leveling) cylinders on Crawler
Transporter No. 2. Technicians have removed and replaced 14 of the 32
bearings and reinstalled the seven cylinders in Crawler No. 2. Four
additional cylinders are in the process of being refurbished. Two more
cylinders will be removed today. The remaining bearings will be manufactured
and delivered in time to support the scheduled rollout for an Oct. 2 launch.

MISSION: STS-113 – 16th ISS Flight (11A) – ITS, P1


VEHICLE: Endeavour/OV-105

TARGET LAUNCH DATE: Nov. 2, 2002 NET

TARGET LANDING DATE: Nov. 13, 2002

MISSION DURATION: 11 days

CREW: Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox,
Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev

ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Processing continues for Endeavour’s launch to the
International Space Station. Main Propulsion System flow liner crack welding
has been successfully completed. Preparations for Space Shuttle Main Engine
installation are in work with engine installation beginning as early as this
evening.

MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE – Columbia/OV-102

TARGET LAUNCH DATE: Jan. 16, 2003 NET

TARGET LANDING DATE: TBD

MISSION DURATION: 16 days

CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon

ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees

Shuttle Processing Note: Nominal processing has been completed in
preparation for Columbia’s research mission now scheduled for no earlier
than Jan. 16.

ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: Sept. 1 has been identified as the date to begin
Discovery’s Orbiter Major Modification period at KSC.