Space Shuttle Processing Status 25 Sep 2002

By SpaceRef Editor
September 25, 2002
Filed under , ,

MISSION STS-112 — 15TH ISS FLIGHT (9A) – S1 Truss

  • VEHICLE:Atlantis/OV-104
  • TARGET LAUNCH DATE:Oct. 2, 2002 NET
  • TARGET LAUNCH PERIOD:2 – 6 p.m. EDT
  • TARGET LANDING DATE:Oct. 13, 2002
  • MISSION DURATION:11 days
  • CREW:Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
  • ORBITAL ALTITUDE AND INCLINATION:122 nautical miles, 51.6 degrees

Shuttle Processing Note: Final preparations for Atlantis’ lift-off to the International Space Station next week continue on schedule. Final ordinance operations are complete. Launch countdown preparations and aft closeouts continue, and the Extravehicular Mobility Units are being installed today. Mission managers continue to monitor several tropical storms though none are expected in the KSC vicinity in the near term and no work is being held up as we proceed on schedule for launch.

MISSION: STS-113 – 16th ISS Flight (11A) – P1 Truss Segment

  • VEHICLE:Endeavour/OV-105
  • TARGET LAUNCH DATE:Nov. 10, 2002 NET
  • TARGET LANDING DATE:Nov. 20, 2002
  • MISSION DURATION:11 days
  • CREW:Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev
  • ORBITAL INSERTION ALTITUDE AND INCLINATION:122 nautical miles/51.6 degrees

Shuttle Processing Note:Endeavour’s forward closeouts continue in work. The functional retest on adjustments made on the Manipulator Positioning Mechanism that is attached to the Remote Manipulator System was successful. Payload bay doors have been closed in preparation for rollover and mate to the external tank.

MISSION STS-107 –SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

  • VEHICLE –Columbia/OV-102
  • TARGET LAUNCH DATE:Jan. 16, 2003 NET
  • TARGET LANDING DATE:Feb. 1, 2003
  • MISSION DURATION:16 days
  • CREW:Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon
  • ORBITAL INSERTION ALTITUDE AND INCLINATION:150 nautical miles/39 degrees

Shuttle Processing Note: Columbia continues processing in preparation for its research mission scheduled for no earlier than Jan. 16. 

 
ORBITER MAJOR MODIFICATION PERIOD
VEHICLE: Discovery/OV-103

Shuttle Processing Note:The Orbiter Major Modification (OMM) period forDiscovery is underway with radiator removal and nose landing gear retraction. Wire inspections continue and will be performed throughout the entire vehicle during the OMM.