Space Shuttle Processing Status 25 Apr 2002
MISSION: STS-111 – 14th ISS Flight (UF2) – MPLM
VEHICLE: Endeavour/OV-105
LAUNCH DATE: May 30, 2002
KSC LANDING DATE: June 11, 2002
MISSION DURATION: 11 days
CREW: Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS up) Korzun, Whitson, Treschev; (ISS down) Onufrienko, Bursch, Walz
ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees
Shuttle Processing Note: Shuttle Endeavour has been mated to the External Tank/Solid Rocket Boosters in the Vehicle Assembly Building (VAB) and the Shuttle Interface Test is being conducted to verify overall status of the STS-111 space vehicle. Final preparations will begin on Friday for Endeavour’s rollout to the launch pad next week.
MISSION STS-107 -SPACEHAB/ FREESTAR RESEARCH MISSION
VEHICLE -Columbia/OV-102
LAUNCH DATE: July 19, 2002
KSC LANDING DATE: August 4, 2002
MISSION DURATION: 16 days
CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon
ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 deg
Shuttle Processing Note: In the Orbiter Processing Facility (OPF), the Extended Duration Orbiter pallet has been installed aboard Shuttle Columbia. Shuttle managers have made the decision to change out and retest a cold plate in Payload Bay 5 after several dings were discovered on the plate surface. Freon Coolant Loop No. 2 will be drained today to accommodate the cold plate changeout. Columbia will remain powered down until the cold plate is re-installed and the two freon loops are re-serviced.
MISSION STS-112 — 15TH ISS FLIGHT (9A) – BA, ITS S1
VEHICLE: Atlantis/OV-104
LAUNCH DATE: August 22, 2002
KSC LANDING DATE: September 1, 2002
MISSION DURATION: 10 days
CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin
ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees
Shuttle Processing Note: De-servicing of Shuttle Atlantis is ongoing in the OPF following the orbiter’s return from the highly successful STS-110 mission last week. The heat shield has been removed and preparations are in work to remove the Space Shuttle Main Engines early next week.
ORBITER MAJOR MODIFICATION PERIOD
VEHICLE: Discovery/OV-103
Shuttle Processing Note: Discovery rolled back to the OPF yesterday after a brief storage period in the VAB. The orbiter is scheduled to begin its Major Modification period late this summer.