Space Shuttle Processing Status 24 May 2001

By SpaceRef Editor
May 24, 2001
Filed under , ,

MISSION: STS-104 – 10th ISS Flight (7A) – Airlock

VEHICLE: Atlantis/OV-104

LOCATION: Orbiter Processing Facility (OPF) bay 3

TARGET KSC LAUNCH DATE/TIME: NET June 20, 2001 at about 1:45 p.m. EDT

TARGET KSC LANDING DATE/TIME: July 1, 2001

MISSION DURATION: 11 days

CREW: Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Orbiter Atlantis remains in OPF bay 3 today while
technicians continue tile-drying efforts. It is expected that Atlantis will
roll over to the Vehicle Assembly Building no earlier than Tuesday, May 29.
As a result, the target launch date has been reset for no earlier than June
20.

In the OPF, engineers continue to evaluate orbiter Atlantis’ thermal
protection system while technicians use clusters of 200-300 watt heat lamps
to dry or “bake” about 600 Shuttle tiles. The orbiter was exposed to
significant rainfall while at Edwards Air Force Base, Calif., following its
landing there in February, at the conclusion of mission STS-98.

At this time, the drying work is focused on the black tile located below the
leading edge of the orbiter’s right wing. Tile baking is also in work near
the left-hand main landing gear door. Engineers are evaluating the current
procedures to assure the tiles are in a safe and flight-ready condition. A
wet tile can freeze in orbit and possibly debond or separate from the
orbiter during reentry.

Payload Processing Note: The U.S. Airlock is currently at the pad in the
payload changeout room. Minimal work will be conducted through the time the
orbiter arrives at the pad on or about June 2. The airlock will be installed
into the orbiter’s payload bay once Atlantis is at the pad and final
closeouts for flight will commence. The date for the crew’s Terminal
Countdown Demonstration Test is under review.

MISSION: STS-105 – 11th ISS Flight (7A.1) – Leonardo MPLM

VEHICLE: Discovery/OV-103

LOCATION: OPF bay 2

TARGET KSC LAUNCH DATE/TIME: July 12, 2001 at 5:22 a.m. EDT

TARGET KSC LANDING DATE/TIME: July 23, 2001

MISSION DURATION: 11 days

CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov,
Turin; (ISS down) Usachev, Voss, Helms,

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Technicians have completed Discovery’s potable
water system servicing. Workers are currently checking the water spray
boilers. Engine heat shield installation is in work, along with
communication system checks.

Payload Processing Note: Experiment and supply rack installations continue
on the Leonardo Multi-Purpose Logistics Module (MPLM) in the Space Station
Processing Facility.

MISSION: STS-108 – 12th ISS Flight (UF1) -Raffaello MPLM

VEHICLE: Endeavour/OV-105

LOCATION: Orbiter Processing Facility bay 1

TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001

TARGET KSC LANDING DATE/TIME: Dec. 9, 2001

MISSION DURATION: 10 days

CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS
down) Culbertson, Dezhurov, Turin

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Forward reaction control system checks are ongoing,
and engine heat shield removal is in work. Technicians are preparing to
remove Endeavour’s three main engines this week.

MISSION: STS-109 – HST Servicing Mission 3B

VEHICLE: Columbia/OV-102

LOCATION: Vehicle Assembly Building high bay 4

TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002

TARGET KSC LANDING DATE/TIME: Jan. 28, 2002

MISSION DURATION: TBD

CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino

ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees

Shuttle Processing Note: Columbia was moved to the VAB transfer aisle early
this morning to accommodate external tank move operations. Columbia will
move into OPF bay 3 when Atlantis rolls over to the VAB.