Status Report

Space Shuttle Processing Status 2 May 2002

By SpaceRef Editor
May 2, 2002
Filed under , ,

MISSION: STS-111 – 14th ISS Flight (UF2) – MPLM

VEHICLE: Endeavour/OV-105

LAUNCH DATE: May 30, 2002

LAUNCH PERIOD: 4-8 p.m. EDT

KSC LANDING DATE: June 11, 2002

MISSION DURATION: 11 days

CREW: Cockrell, Lockhart, Chang-Diaz, Perrin; (ISS up) Korzun, Whitson, Treschev; (ISS down) Onufrienko, Bursch, Walz

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: At Pad A, launch pad validations and the Space Shuttle Main Engine Flight Readiness Test were completed for Endeavour’s scheduled mission on May 30. Preparations for the helium signature test are underway. The payload bay doors are scheduled to be opened today for the installation of the Leonardo Multi Purpose Logistics Module on Monday.

MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE -Columbia/OV-102

LAUNCH DATE: July 19, 2002

KSC LANDING DATE: August 4, 2002

MISSION DURATION: 16 days

CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon

ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 deg

Shuttle Processing Note: In the Orbiter Processing Facility (OPF), preparations continue with Columbia for the STS-107 research mission. Leak checks of the two Freon Coolant Loops are complete and servicing of Freon Coolant Loop No. 2 is scheduled for tomorrow. Checks of the newly installed cold plate in Bay 5 and installation of windows No. 5 and 7 are in work. Columbia will be powered up on Monday in preparation for the Payload Premate Test scheduled for next week.

MISSION STS-112 — 15TH ISS FLIGHT (9A) – BA, ITS S1

VEHICLE: Atlantis/OV-104

LAUNCH DATE: August 22, 2002

KSC LANDING DATE: September 1, 2002

MISSION DURATION: 10 days

CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin

ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note: Atlantis is continuing its deservicing in the OPF for the August launch to the International Space Station. Forward Reaction Control System checkout is scheduled for today and residual fuel in the Orbital Maneuvering System and Auxiliary Power Units was drained yesterday.

ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103


Shuttle Processing Note: Discovery is in the OPF awaiting the start of its Orbiter Major Modification (OMM) period that is scheduled to begin at the Kennedy Space Center late this summer.

SpaceRef staff editor.