Status Report

Space Shuttle Processing Status 2 Jul 2001

By SpaceRef Editor
July 2, 2001
Filed under , ,

MISSION: STS-104 – 10th ISS Flight (7A) – Airlock

VEHICLE: Atlantis/OV-104

LOCATION: Launch Pad 39B

KSC LAUNCH DATE/TIME: July 12, 2001 at 5:04 a.m. EDT

KSC LANDING DATE/TIME: July 23, 2001 at 12:57 a.m.

MISSION DURATION: 10 days and 19 hours and 53 minutes

CREW: Lindsey, Hobaugh, Kavandi, Gernhardt, Reilly

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Preparation for the launch of Space Shuttle
Atlantis continues at Launch Pad 39B. Last week’s Flight Readiness Review
confirmed the July 12 launch date.

The flight crew’s Terminal Countdown Demonstration Test concluded last week
and the orbiter’s payload bay doors have been closed for flight. Workers
completed prelaunch propellant loading activities today. The flight crew’s
space suits are being installed and functional checks follow tomorrow.
Shuttle ordnance installation is in work through tomorrow and aft engine
compartment closeouts conclude Sunday, June 8.

MISSION: STS-105 – 11th ISS Flight (7A.1) – Leonardo MPLM

VEHICLE: Discovery/OV-103

LOCATION: Launch Pad 39A

TARGET KSC LAUNCH DATE/TIME: NET August 5, 2001at 7:05 p.m. EDT

TARGET KSC LANDING DATE/TIME: August 17, 2001 at about 3:30 p.m.

MISSION DURATION: 11 days , 20 hours and 25 minutes

CREW: Horowitz, Sturckow, Barry, Forrester; (ISS up) Culbertson, Dezhurov,
Turin; (ISS down) Usachev, Voss, Helms,

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Space Shuttle Discovery began rolling out to the
launch pad today at 1:28 a.m. and was hard down on the pad surface at 7:42
a.m. Launch pad validations are in work through Tuesday. Workers will
replace several main engine transducers prior to the planned engine flight
readiness test slated for later this week.

MISSION: STS-108 – 12th ISS Flight (UF1) – MPLM

VEHICLE: Endeavour/OV-105

LOCATION: Orbiter Processing Facility bay 1

TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001 EST

TARGET KSC LANDING DATE/TIME: Dec. 9, 2001

MISSION DURATION: 10 days

CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS
down) Culbertson, Dezhurov, Turin

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Technicians have completed inspections of
Endeavour’s forward overhead window frames and body flap this week. While
the vehicle is not powered, workers are performing planned modifications on
orbiter wiring and monoball harnesses. A powered-up checkout is scheduled
to begin July 10.

MISSION: STS-109 – HST Servicing Mission 3B

VEHICLE: Columbia/OV-102

LOCATION: OPF bay 3

TARGET KSC LAUNCH DATE/TIME: Jan. 17, 2002 EST

TARGET KSC LANDING DATE/TIME: Jan. 28, 2002

MISSION DURATION: TBD

CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino

ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees

Shuttle Processing Note: Technicians are inspecting the orbiter’s chin panel
and nose cap. Standard subsystem testing is ongoing.

SpaceRef staff editor.