Status Report

Space Shuttle Processing Status 15 Oct 2001

By SpaceRef Editor
October 15, 2001
Filed under , ,


MISSION: STS-108 – 12th ISS Flight (UF1) – MPLM

VEHICLE: Endeavour/OV-105

TARGET KSC LAUNCH DATE/TIME: Nov. 29, 2001 at 7:35 p.m. EST

TARGET KSC LANDING DATE/TIME: Dec. 10, 2001 at 2:56 p.m.

MISSION DURATION: 11 days

CREW: Gorie, Kelly, Godwin, Tani; (ISS up) Onufrienko, Bursch, Walz; (ISS
down) Culbertson, Dezhurov, Tyurin

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Processing continues on schedule toward next week’s
planned orbiter/external tank mate operation. Leak checks of Endeavour’s
crew module and external airlock are complete. Auxiliary power unit
controller checks are also complete.

Last Friday, Endeavour’s payload bay doors were cycled and over the weekend
the orbiter’s midbody was cleaned. Today, technicians will close the
orbiter’s payload bay doors in preparation for rollout. Closeouts continue
in the forward and aft compartments.

MISSION: STS-109 – HST Servicing Mission 3B

VEHICLE: Columbia/OV-102

TARGET KSC LAUNCH DATE/TIME: Feb. 14, 2002 at 1:43 p.m. EST

TARGET KSC LANDING DATE/TIME: Feb. 25, 2002 at 11:40 a.m.

MISSION DURATION: 11 days

CREW: Altman, Carey, Grunsfeld, Currie, Newman, Linnehan, Massimino

ORBITAL INSERTION ALTITUDE and INCLINATION: 308 nautical miles/28.5 degrees

Shuttle Processing Note: Over the weekend, technicians completed alignment
work on the heads-up display (HUD) located on the commander’s side of
Columbia’s cockpit. This coming weekend, workers will complete the same
work on the pilot’s HUD. Auxiliary power unit leak checks are in work this
week, along with orbiter maneuvering system electrical verifications.

MISSION: STS-110 – 13th ISS Flight (8A) – ITS S0, MT

VEHICLE: Atlantis/OV-104

TARGET KSC LAUNCH DATE/TIME: March 21, 2002

TARGET KSC LANDING DATE/TIME: March 30, 2002

MISSION DURATION: 11 days

CREW: Bloomfield, Frick, Ross, Smith, Ochoa, Morin, Walheim

ORBITAL INSERTION ALTITUDE and INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Workers have begun planned powered down
modifications on orbiter Atlantis. This week, work to upgrade the orbiter’s
mass memory units is under way. Technicians are also replacing window No.
7. Atlantis will resume powered work in mid-December.

STRUCTURAL INSPECTION & MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: Orbiter Discovery remains in temporary storage
through late October. Discovery is scheduled to begin a thorough structural
inspection and modification period. Shuttle managers continue to assess the
content, schedule and location of this planned work period.

SpaceRef staff editor.