Space Shuttle Processing Status 12 Feb 2001

By SpaceRef Editor
February 12, 2001
Filed under ,

MISSION: STS-98 — 7th ISS Flight (5A) – U.S. Laboratory

Vehicle Atlantis/OV-104

Location on orbit

KSC Launch Date/Time Feb. 7, 2001 at 6:13:02 p.m. EST

Target KSC Landing Date/Time Feb. 18, 2001 at about 12:52 p.m. EST

Launch Window less than 5 minutes

Mission Duration 10 days, 18 hours and 39 minutes

Crew Cockrell, Polansky, Curbeam, Jones, Ivins

Orbit Altitude and Inclination 173 nautical miles/51.6 degrees

Shuttle Processing Note (mission processing summary)

Shuttle Atlantis is performing well on orbit. Routine post-flight inspection
of the STS-98 solid rocket boosters (SRB) began this morning. Preliminary
reports indicate that both boosters are in good condition. SRB open
assessment will continue through next week.

MISSION: STS-102 — 8th ISS Flight (5A.1) – Leonardo MPLM

Vehicle Discovery/OV-103

Location Launch Pad 39B

Target KSC Launch Date/Time March 8, 2001, at 6:45 a.m. EST

Target KSC Landing Date/Time March 20, 2001, at 1:13 a.m. EST

Launch Window less than 5 minutes

Mission Duration 11 days, 18 hours, 28 minutes

Crew Wetherbee, Kelly, Thomas, Richards; (up) Voss, Helms, Usachev; (down)
Shepherd, Gidzenko, Krikalev

Orbit Altitude and Inclination 122 nautical miles/51.6 degrees

Shuttle Processing Note

Space Shuttle Discovery rolled out of Vehicle Assembly Building high bay 1
today at 7:10 a.m. and was hard down on the pad surface at 1:35 p.m. Launch
pad validations are in work through Tuesday night. The seven-member flight
crew arrives this week to participate in Terminal Countdown Demonstration
Test activities including a launch day dress rehearsal on Thursday. The MPLM
payload, “Leonardo,” is scheduled to arrive at the pad Feb. 23 for
installation into Discovery’s payload bay.
Upcoming Milestones (dates are targets only)


  • Terminal Countdown Demonstration Test complete February 15
  • Prelaunch orbiter propellant load begins February 20
  • Payload arrives at Pad 39B February 23
  • MPLM installed into Discovery’s payload bay February 26

MISSION: STS-100 — 9th ISS Flight (6A) – Raffaello MPLM, SSRMS

Vehicle Endeavour/OV-105

Location Orbiter Processing Facility (OPF) bay 2

Target KSC Launch Date/Time April 19, 2001, at 2:04 p.m. EDT

Target KSC Landing Date/Time April 30, 2001, at 9:56 a.m. EDT

Mission Duration 11 days

Crew Rominger, Ashby, Hadfield, Parazynski, Phillips, Guidoni, Lonchakov
Orbit Altitude and Inclination 173 nautical miles/51.6 degrees

Shuttle Processing Note

Endeavour’s fuel cell voltage test is complete. The left-hand orbital
maneuvering system pod is installed, and workers today are verifying the
Shuttle’s robot arm. Technicians will service Endeavour’s freon coolant
system No. 1 this week. Tonight, work begins to install the Shuttle’s three
main engines.