Status Report

Rosetta Status Report for week 10 to 17 September 2004

By SpaceRef Editor
September 23, 2004
Filed under , ,
Rosetta Status Report for week 10 to 17 September 2004
http://images.spaceref.com/news/rosetta.jpg

Ongoing Payload Commissioning

In the reporting period the payload commissioning activities continued, with the first part of the Pointing Scenario, covering two days of VIRTIS operations with MIRO, MIDAS and RSI activities, the final MIDAS functional commissioning and the start of the OSIRIS functional commissioning. All activities have been executed according to schedule and completed successfully.

Full daily passes over the New Norcia station were taken throughout the week, with the addition of one weekly pass of 4 hours over a DSN station (DSS-15) on 16 September.

The table below shows a chronology of the main activities in the reporting period:









































Mission Day


Date


DOY


Main Activity


193


10/11.09.04

254/255 Pointing pass 1

194


11/12.09.04

255/256 Pointing pass 2

195


12/13.09.04

256/257 MIDAS commissioning pass 1

196


13/14.09.04

257/258 MIDAS commissioning pass 2

197


14/15.09.04

258/259 OSIRIS commissioning pass 1

198


15/16.09.04

259/260 OSIRIS commissioning pass 2

199


16/17.09.04

260/261 OSIRIS commissioning pass 3

At the end of the last New Norcia pass in the reporting period (DOY 261) Rosetta was at 74.2 million km from the Earth. The one-way signal travel time was 4 minutes 7 seconds.

SpaceRef staff editor.