Status Report

NOAA SATOPS Morning Report: Wednesday, June 08, 2005

By SpaceRef Editor
June 8, 2005
Filed under ,

DAY 159

DMSP

All DMSP operations were nominal over the past 24 hours.

POES

All POES operations were nominal over the past 24 hours.

GOES

GOES 11/GOES 12 1100Z-1240Z on June 7 – Thunderstorm in area, a lightening strike in the vicinity of building prompted SOCC crews to hand operations over to Wallops CDA while ground systems were checked out. Several backup systems were impacted and brought back on line. No data losses attributed to activity and all equipment back to full operational status. SOCC now back in control.

All GOES operations were nominal over the past 24 hours.

Questions or comments to Keith.Amburgey@noaa.gov

SpaceRef staff editor.