JDay 221

NOTE TO GOES LRIT USERS:

NOAA’s OSDPD LRIT Office & Wallops CDA have worked out a strategy to isolate corruption introduced through the LRIT space link from corruption introduced through the actual generation of the product, but it requires timely notification of data dropouts. All LRIT data users are encouraged to report problems directly to the following LRIT email distribution list: NOAA Low Rate Information System

FCDAS planned power outage scheduled from 2000z-2300z.

GOES

All GOES operations were nominal over the past 24 hours. No anomalies affecting product delivery or s/c health & safety. For GOES status and other information please see: http://www.oso.noaa.gov/goes/index.htm

POES

N17 rev 21429 at Fairbanks time 23:07:20 was not supported due to all equipment not being returned to service from planned power outage. All data was recovered on up coming passes with the exception of GAC 2A. DTR management prevented additional data recovery attempts.

From 2330z until 0149z the narrow band link between FCDAS and SOCC remained down. All data was recovered during real-time at FCDAS. A N-17 LAC was lost when the data could not be recovered from the IMUX recorder on the ground. Reason is unknown at this time.

All other POES operations were nominal over the past 24 hours. No anomalies affecting product delivery or s/c health & safety. For a detailed status and description of POES see: http://www.oso.noaa.gov/poes/index.htm

DMSP

All DMSP operations were nominal over the past 24 hours. No anomalies affecting product delivery or s/c health & safety. For more DMSP Information please see: http://dmsp.ngdc.noaa.gov/dmsp.html