NOAA SATOPS Morning Report: Tuesday, March 13, 2012
Customers or users who want to call to ask about problems or report outages can use the following contacts:
– For questions about data quality (noisy data, dropouts, schedules), GOES or POES products, or status of spacecraft can call the SAB Shift Supervisor at 301-763-8444
– To report an outage or document a problem, call the ESPC Operations Crew Lead at 301-457-5218. All LRIT data users are encouraged to report problems to: LRIT@noaa.gov
DOY 073
GOES
GOES-12 DOY73 image frame breaks at 1047Z and 1053Z, and 2154Z due to RFI at WCDA. Under investigation.
All other GOES operations were nominal over the past 24 hours.
No anomalies affecting product delivery via GVAR or s/c health & safety.
For GOES status and other information please see:
http://www.oso.noaa.gov/goes
POES
All POES operations were nominal over the past 24 hours.
No anomalies affecting product delivery or s/c health & safety.
For a detailed status and description of POES see:
http://www.oso.noaa.gov/poes
DMSP
All DMSP operations were nominal over the past 24 hours.
No anomalies affecting product delivery or s/c health & safety.
For more DMSP Information please see:
http://dmsp.ngdc.noaa.gov/dmsp.html
JASON-2
All JASON-2 operations were nominal over the past 24 hours.
No anomalies affecting product delivery or s/c health & safety.
ESPC Reported data outage and delays
DOY72-73 23:13z through 09:44z. ESPC did not receive 1/2 orbit Metop data from McMurdo for approximately 10hrs due to a Eumetsat ground system anomaly. All data (full orbit) was recovered from Svalbard.
Questions or comments to Ron.Mahmot@noaa.gov