NOAA SATOPS Morning Report: Tuesday, January 03, 2006

Day 003
DMSP
All DMSP operations were nominal over the past 96 hours.
No anomalies affecting product delivery or s/c health & safety.
Leap second and change of year transition went smoothly.
For more DMSP Information please see: http://dmsp.ngdc.noaa.gov/dmsp.html
POES
All POES operations were nominal over the past 96 hours.
No anomalies affecting product delivery or s/c health & safety.
Leap second and change of year transition went smoothly.
For a detailed status and description of POES see: http://www.oso.noaa.gov/poes/index.htm
GOES
All GOES operations were nominal over the past 96 hours.
No anomalies affecting product delivery or s/c health & safety.
Leap second transition went smoothly.
Minor problem with change of year transition affected one image.
For GOES Status and other information please see: http://www.oso.noaa.gov/goes/index.htm
Questions or comments to Keith.Amburgey@noaa.gov