NOAA SATOPS Morning Report: Tuesday, February 19, 2008
Customers or users who want to call to ask about problems or report outages can use the following contacts:
– For questions about data quality (noisy data, dropouts, schedules), GOES or POES products, or status of spacecraft can call the SAB Shift Supervisor at 301-763-8444
– To report an outage or document a problem, call the ESPC Operations Crew Lead at 301-457-5218. All LRIT data users are encouraged to report problems to: LRIT@noaa.gov
J050
GOES
All GOES operations were nominal over the past 96 hours. No anomalies affecting product delivery or s/c health & safety. For GOES status and other information please see: http://www.oso.noaa.gov/goes/index.htm
POES
NOTE: NWS is receiving N17 HRPT from FCDA and Barrow while N17 is on STX2
NWS is now receiving and ingesting HRPT from the FCDAS and Barrow supports. All data sets are being dropped into AWIPS by UAF.
N18 J48 00:41Z GAC3A delivered late to EUMETSAT due to IMUX problems at FCDA N15 J49 12:19Z Lost approx. 10% of GAC1A due to RF problems over Wallops. Under investigation.
POES operations were nominal over the past 96 hours No anomalies affecting product delivery or s/c health & safety. For a detailed status and description of POES see: http://www.oso.noaa.gov/poes/index.htm
DMSP
OPS49 J48 02:35Z CATIII data loss of 222 PB seconds due to a bit sync problem at the FCDA
OPS49 J49 03:52Z CATII data loss of 122PB seconds due to a POGO ground station problem
OPS49 J49 02:10Z CATII data loss of 197PB seconds due to a POGO ground station problem
All DMSP operations were nominal over the past 96 hours. No anomalies affecting product delivery or s/c health & safety. For more DMSP Information please see: http://dmsp.ngdc.noaa.gov/dmsp.html
Questions or comments to Ron.Mahmot@noaa.gov