Customers or users who want to call to ask about problems or report outages can use the following contacts:

– For questions about data quality (noisy data, dropouts, schedules), GOES or POES products, or status of spacecraft can call the SAB Shift Supervisor at 301-763-8444

– To report an outage or document a problem, call the ESPC Operations Crew Lead at 301-457-5218. All LRIT data users are encouraged to report problems to: LRIT@noaa.gov

DOY 245

GOES
All GOES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For GOES status and other information please see:
http://www.oso.noaa.gov/goes

POES
NOTE: Due to the hurricane Earl high wind forecast in the Walllops area the 13Meter antennas which support POES will be stowed on DOY
246. Supports scheduled at he WCDA site between 04:00z and 23:00z
are being rescheduled, where possible, at Fairbanks or Svalbard. (for NOAA-19).

All other POES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For a detailed status and description of POES see:
http://www.oso.noaa.gov/poes

DMSP
All DMSP operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For more DMSP Information please see:
http://dmsp.ngdc.noaa.gov/dmsp.html

JASON-2
NOTE: Due to the hurricane Earl high wind forecast in the Walllops area the WCDA 13Meter antennas which support Jason-2 will be stowed on
DOY 246. Jason-2 supports scheduled at WCDA between 04:00z and
23:00z are being rescheduled at Fairbanks.

All other JASON-2 operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety