DOY 104

GOES
NOTE: All GOES spacecraft have entered eclipse season. For keep out zone schedules see: http://www.ssd.noaa.gov/PS/SATS/eclipse.html

All GOES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For GOES status and other information please see:
http://www.oso.noaa.gov/goes

POES
Note: Intermittent problem with POES workstations hanging. Under
investigation.

N19 DOY 102 14:22Z Engineers commanded SARR channel switch to the B-side.

All other POES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For a detailed status and description of POES see:
http://www.oso.noaa.gov/poes

DMSP
All DMSP operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For more DMSP Information please see:
http://dmsp.ngdc.noaa.gov/dmsp.html

JASON-2
DOY 103 Unsuccessful data recovery on revs 13159 and 13160 due to
connection problems with the Usingen Ground Station. All data
recovered on subsequent revs.

All other JASON-2 operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety

ESPC Reported data outage and delays
DOY 104 N-18 HRPT REV. #30383 from Cape Ferguson was lost.

DOY 102 HRPT from Cape Ferguson not received: The N-15 pass rev. 67141
beginning at 1806Z, N-15 pass rev. 67142, and N-17 pass rev. 45736 at