Status Report

NOAA SATOPS Morning Report: Sunday, August 28, 2011

By SpaceRef Editor
August 29, 2011
Filed under , ,

Customers or users who want to call to ask about problems or report outages can use the following contacts:

– For questions about data quality (noisy data, dropouts, schedules), GOES or POES products, or status of spacecraft can call the SAB Shift Supervisor at 301-763-8444

– To report an outage or document a problem, call the ESPC Operations Crew Lead at 301-457-5218. All LRIT data users are encouraged to report problems to: LRIT@noaa.gov

DOY 240

NOTES: In preparation for Hurricane Irene, WCDA personnel stowed the following antennas: 13M-A, 13M-B, 26M, 14.2M, 18M-A, and 18M-B. POES & Jason-2 supports at WCDA were ceased on DOY239 at 13:44z. Additional IJPS Svalboard supports were used to cover N19 gaps and FCDA was used as much as possible to cover the secondary POES missions(N15 – N18). GOES-11 was successfully moved to FCDA at 15:12z. GOES-14 was moved to USN’s Hawaii ground station at 01:50z on DOY240. On-call day staff personnel were on-site at WCDA, WBU, and NSOF in order to quickly address any problems during the night.

NSOF has been on generator power since approximately 03:20z. The decision was made to switch from commercial power due to the frequent short duration power hits that had been occurring during the storm.

GOES
GOES-11 DOY239 13:30z – 15:12z failover from WCDA to FCDA. The following images/soundings were missed: images – 13:51z,14:00z, and 14:45z; sounding – 14:01z

All other GOES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For GOES status and other information please see:
http://www.oso.noaa.gov/goes

POES
NOTES: POES supports at WCDA are scheduled to resume on Monday.

N18 DOY238 20:20z unable to recover GAC3B from WCDA. Under investigation.

N18 DOY238 22:09z missed GAC3B due to a scheduling problem. Under investigation.

N18 DOY239 no GAC recorded between 03:17z and 07:03z due to a scheduling problem. Under investigation.

All other POES operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For a detailed status and description of POES see:
http://www.oso.noaa.gov/poes

DMSP
NOTES: There were no DMSP supports affected as a result of the storm.

All other DMSP operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety.
For more DMSP Information please see:
http://dmsp.ngdc.noaa.gov/dmsp.html

JASON-2
NOTES: There were no data losses as a result of moving all scheduled Jason-2 WCDA supports to either Usingen or FCDA. In a few cases latency requirements were not met.

All other JASON-2 operations were nominal over the past 48 hours.
No anomalies affecting product delivery or s/c health & safety

ESPC Reported data outage and delays
DOY239 GOES-11 images lost 13:51z, 14:00z, 14:45z
DOY239 GOES-11 sounding lost 14:01z

Questions or comments to Ron.Mahmot@noaa.gov

SpaceRef staff editor.