Note: NASA’s Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads. If you are a member of the media and would like further information, visit: http://www.nasa.gov/centers/kennedy/news/index.html

Mission: STS-122 – 24th International Space Station Flight – Columbus laboratory
Vehicle: Atlantis (OV-104)
Location: Launch Pad 39A
Launch Date: Targeting Feb. 7
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Launch Pad 39A

  • Engine cutoff (ECO) sensor external feedthrough connector
  • installation is complete
  • Aft ECO instrumentation wiring removal and retest was completed
  • All sensors have been tested successfully
  • ECO sensor feedthrough foaming work on the external J-Box and solid rocket booster PAL ramp continues through the weekend
  • Annual slidewire basket pad evacuation system maintenance and checkout continues through the weekend
  • Solid rocket booster hydraulic retesting was completed Monday
  • Liquid oxygen storage tank pressurization and relief valve testing
  • was successfully completed Tuesday

Mission: STS-123 – 25th International Space Station Flight – Kibo, Dextre
Vehicle: Endeavour (OV-105)
Location: Orbiter Processing Facility Bay 2
Launch Date: Targeting Mid-March
Launch Pad: 39A
Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Orbiter Processing Facility Bay No. 2

  • Removal and replacement work on the purge, vent and drain valve, which is part of the non-breathing air conditioning system completed Thursday
  • Landing gear was retracted
  • Potable water servicing samples completed Wednesday
  • Main landing gear struts’ weight on wheels leak check completed

Vehicle Assembly Building High Bay No. 1

  • External tank/solid rocket booster closeout operations continue
  • Re-foaming of the external tank assembly ring, that goes around the
  • solid rocket boosters near the aft most SRB field joint, is being worked Friday
  • ECO sensor system feed through work begins again Jan. 23

Mission: STS-124 – 26th International Space Station Flight – Kibo Pressurized Module, Japanese Remote Manipulator System
Vehicle: Discovery (OV-103)
Location: Orbiter Processing Facility Bay 3
Launch Date: Targeting April 24
Launch Pad: 39A
Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide, Chamitoff
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Orbiter Processing Facility Bay No. 3

  • Vernier thruster pressure chamber flushes continue in preparation for inspections
  • Ku band antenna stow scheduled for Friday
  • Drag chute flight door checkout scheduled for Friday
  • Solid rocket booster stacking scheduled for Jan. 31
  • Power redundancy testing was successfully completed
  • External tank separation camera interface verification is complete
  • Payload premate testing completed Tuesday