NASA Space Shuttle Processing Status Report 11 January 2008

Note: NASA’s Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads. If you are a member of the media and would like further information, visit: http://www.nasa.gov/centers/kennedy/news/index.html
Mission: STS-122 – 24th International Space Station Flight – Columbus laboratory
Vehicle: Atlantis (OV-104)
Location: Launch Pad 39A
Launch Date: Targeting Feb. 7
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Launch Pad 39A
– Engine cutoff (ECO) sensor external connector replacement hardware was cleared for installation and arrived at the pad. Installation is tentatively scheduled to begin Saturday
– Testing of the faulty ECO sensor system connector hardware continues at Marshall Space Flight Center
– Space shuttle main engine ball seal leak checks performed Thursday with no issues
– Ascent thrust vector controller No. 2 was replaced Jan. 5 and retested Jan. 6
– Solid rocket booster hydraulic retest scheduled for today
Mission: STS-123 – 25th International Space Station Flight – Kibo, Dextre
Vehicle: Endeavour (OV-105)
Location: Orbiter Processing Facility Bay 2
Launch Date: Targeting Mid-March
Launch Pad: 39A
Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Orbiter Processing Facility bay No. 2
– Shuttle orbiter galley functional checks completed today with no issues
– Removal and replacement work will take place on the purge, vent and drain valve, which is part of the non-breathing air conditioning system, Jan. 14-18
– Nose landing gear strut hydraulic level checks and pressurization for flight performed Wednesday
– Main landing gear struts’ weight on wheels leak check scheduled for Monday
Vehicle Assembly Building high bay No. 1
– External tank/solid rocket booster mate in progress
– External tank is hard mated
– Closeout operations continue through this weekend
– Preparation for ECO sensor external connector replacement will take place Saturday and Sunday
Mission: STS-124 – 26th International Space Station Flight – Kibo
Pressurized Module, Japanese Remote Manipulator System
Vehicle: Discovery (OV-103)
Location: Orbiter Processing Facility Bay 3
Launch Date: Targeting April 24
Launch Pad: 39A
Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Orbiter Processing Facility bay No. 3
– Thermal control system checkout completed with no anomalies
– Drag chute alignment and installation completed Thursday
– Space shuttle main engine No. 1 liquid oxygen transducer leak checks performed Thursday with nominal results
– Solid rocket booster stacking date selection expected Jan. 14
– Aft bulkhead check valve retest completed Wednesday with no issues