Note: NASA’s Kennedy Space Center issues Space Shuttle Processing Status Reports periodically and is the source for information regarding processing activities associated with the vehicles and payloads. If you are a member of the media and would like further information, visit: http://www.nasa.gov/centers/kennedy/news/index.html

Mission: STS-122 – 24th International Space Station Flight – Columbus laboratory
Vehicle: Atlantis (OV-104)
Location: Launch Pad 39A
Launch Date: Feb. 7
Crew: Frick, Poindexter, Schlegel, Eyharts, Love, Melvin, Walheim
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Launch Pad 39A

  • Launch countdown preparations continue.
  • Call to stations is scheduled for Feb. 4 at 4:30 p.m.
  • Payload bay door radiator retract hose issue fix under way
  • Hose located on starboard aft
  • X-rays show hose is in good condition and no leaks were detected
  • Engineers designed tool to guide flex hose back into storage box
  • Technician performing work tested the method Thursday with success
  • Payload bay doors scheduled to close using method on Sunday
  • Orbiter aft closeout was completed Thursday
  • Leak check was performed at the purge port of fuel cell No. 2, where no leaks were detected
  • Flight crew stow operations were conducted

Mission: STS-123 – 25th International Space Station Flight – Kibo, Dextre
Vehicle: Endeavour (OV-105)
Location: Orbiter Processing Facility Bay 2
Launch Date: Targeting March 11
Launch Pad: 39A
Crew: Gorie, Johnson, Linnehan, Doi, Behnken, Foreman, Reisman
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Orbiter Processing Facility Bay No. 2

  • Final roll preparations and aft closeout for rollover under way
  • Orbiter/external tank mate planned for Feb. 11
  • Thermal protection system processing and closeout in process
  • Aft compartment platforms and inspections continue

Vehicle Assembly Building High Bay No. 1

  • Engine cutoff sensor system electrical feed-through connector work is in work
  • External tank is mated with the solid rocket boosters

Mission: STS-124 – 26th International Space Station Flight – Kibo
Pressurized Module, Japanese Remote Manipulator System
Vehicle: Discovery (OV-103)
Location: Orbiter Processing Facility Bay 3
Launch Date: Targeting April 24
Launch Pad: 39A
Crew: Kelly, Ham, Nyberg, Garan, Fossum, Hoshide, Chamitoff
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles

Orbiter Processing Facility Bay No. 3

  • Two reinforced carbon-carbon panels have been installed for flight and two more are in the process of being installed
  • Ku-band antenna was deployed Wednesday
  • Drag chute flight door installation completed Jan. 28

Vehicle Assembly Building High Bay No. 3

  • Solid rocket booster stacking begins Feb. 4