NASA ISS On-Orbit Status 20 June 2013
International Space Station (ISS) Management Center (IMC) Daily Summary Report
Increment 36 Operations – Stage 36-6
06/20/13 4:00 pm Central Daylight Time (CDT)
171/21:00 Greenwich Mean Time (GMT)
New Status: Spinal Ultrasound: Flight Engineer (FE)-5 Parmitano completed his first of three planned Spinal Ultrasound scans with FE-6 Nyberg as the operator and with remote guidance assistance from ground specialists. The Crew Medical Restraint System (CMRS) was used for subject positioning. Spinal Ultrasound aims to use ground and space-based studies to characterize spinal changes during and after spaceflight. Ground based pre- and post-flight Magnetic Resonance Imaging (MRI) and high fidelity ultrasound, combined with in-flight ultrasound will be used to characterize and assign a mission health risk to microgravity-associated spinal alterations for back pain and potential injury.
Systems Operations Data File (SODF) Deploy: FE-3 Cassidy deployed new Warning Books that include X2R12 updates and an EVA Systems Book to support upcoming USOS EVAs. These documents were delivered on Automatic Transfer Vehicle (ATV)4.
ATV4 Cargo Operations: All 3 USOS crew members performed an estimated 13 hours 50 minutes of cargo operations in under 6 hours of actual crew time today, and completed more than had been expected for this week’s ATV4 cargo transfer activities. Following the transfer to and from the ATV, the crew took closeout photos in preparation for ATV4 hatch closure prior to Russian EVA #33 planned for Monday, June 24.
Today’s Planned Tasks
– PROK. Urine РН Test [Complete]
– HRF Urine Sample Collection [Complete]
– HRF – Urine Sample MELFI Insertion [Complete]
– Daily Planning Conference (S-band) [Complete]
– URAGAN. Photo Spectrum System Battery Charge (start) / r/g 2437 [Complete]
– IMS Tagup (S-band) [Complete]
– CIR – Hardware Setup [Complete]
– USND2. Hardware Activation [Complete]
– SPHERES Tank verify [Complete]
– Configure ПхО prior for Pressurized Orlan Suit Translation Training r/g 2667 [Complete]
– Transfer of two Pressurized Orlan Suits to ПхО / r/g 2690 [Complete]
– Assistance in Transfer of two Pressurized Orlan Suits to ПхО / r/g 2690 [Complete]
– SPINAL. Scanning Ops [Complete]
– HRF Urine Sample Collection [Complete]
– HRF – Sample Insertion into MELFI [Complete]
– ТКГ 418 (DC1) Activation / Activation/Deactivation [Complete]
– Configuring ПхО to Initial State after EVA Training / r/g 2667 [Complete]
– Orlan-MK Drink Bag Refill and Install [Complete]
– SPINAL – Scan Photo [Complete]
– SODF Deploy [Complete]
– Installation of Portable Repress Tank prior to EVA [Complete]
– URAGAN. Observation and Photography r/g 2676 [Complete]
– DC1-ТКГ Hatch Closure / Activation/Deactivation [Complete]
– DC1-СУ and СУ-ТГК Hatch Leak Check / Activation/Deactivation [Complete]
– EXPRS3 – Load Application and Configure Laptop for the Experiment [Complete]
– MERLIN3. Application Load [Complete]
– BCAT – Camera Battery Changeout [Complete]
– HRF. Ultrasound 2 HRF Rack 1 Power Off and Stow [Complete]
– IMS and Stowage Conference [Complete]
– Columbus Front Deck Rack Front Restow [Complete]
– SPHERES battery verify [Complete]
– ABRS – Application Load [Complete]
– FIR CVB module inspect [Complete]
– PROK. Diet Logging [Complete]
– PROK. Diet Logging First Time [Complete]
– BLR48. Media Card Exchange [Complete]
– ATV Cargo Operations [Complete]
– ATV Cargo Operations [Complete]
– Installation of additional portable repress tank in DC1 r/g 2686
– SPHERES battery verify [Complete]
– ATV Cargo Operations [Complete]
– СКПФ1, СКПФ2 Dust Filter Replacement and MRM1 ГЖТ Cleaning [Complete]
– Replacement of АСУ Control Panel ПУ-1. r/g [Complete]
– В3 Fan Screen Cleaning in DC1 [Complete]
– EVA Medical Kit Configuration / r/g 2684 [Complete]
– On MCC Go Demating БИТС2-12 telemetry connectors [Complete]
– Replacement of АСУ Control Panel ПУ-1 [Complete]
– Microbial Sample Collection r/g 2641 [Complete]
– ATV – prep for Transfer Tagup [Complete]
– HRF Urine Sample Collection [Complete]
– HRF – Sample Insertion into MELFI [Complete]
– MO-21 Prep. ECOSPHERA Battery Charge / r/g 2640 [Complete]
– ATV Transfer Tagup [Complete]
– IMS Update [Complete]
– HRF – Hardware Setup [In Work]
– Replacement of Dust Collector filters and В1, В2 Fan Screen Cleaning in DC1 [Complete]
– Cleaning ВД1 and ВД2 Air Ducts in DC-1 [Complete]
– СОЖ Maintenance [Complete]
– HRF Urine Sample Collection [Complete]
– HRF – Sample Insertion into MELFI [Complete]
– ATV – Post-Activity Photo [Complete]
– Daily Planning Conference (S-band) [Complete]
– Reading REMINDER [Complete]
– BCAT Reminder [Complete]
Task List
– CEO Ops [Complete]
– WHC KTO replace
– WHC EDV R&R
– Preparation of reports for Roskosmos site
– ECON-M. Observations and Photography
– URAGAN Observations and Photography
– EVA-Connector sleeve locate [In work]
– N1 UOP Reconfig [Complete]
– P/TV Audit Pt 6 [Complete]
Ground
– Nominal Commanding
Three-Day Look Ahead:
Saturday, 6/22: Crew off duty
Sunday, 6/23: Crew off duty
Monday, 6/24: RS EVA #33