NASA ISS On-Orbit Status 13 November 2011

All ISS systems continue to function nominally, except those noted previously or below. Sunday – Crew off duty. Ahead: Week 9 of Increment 29 (three/six-persons crew)

. At Baikonur/Kazakhstan, Soyuz TMA-22/28S is being counted down for tonight’s launch at 11:14pm EST, carrying Expedition 29 crewmembers Dan Burbank (USA), Anton Shkaplerov & Anatoly Ivanishin ( both Russia), for a stay of 123 days as part of Exp-29 and -30. After Mike Fossum, Sergey Volkov & Satoshi Furukawa depart on 11/21 in Soyuz TMA-02M/27S, Burbank will serve as ISS CDR, with Shkaplerov & Ivanishin as FEs.

After wakeup, FE-4 Volkov performed the routine inspection of the SM (Service Module) PSS Caution & Warning panel as part of regular Daily Morning Inspection.

CDR Fossum checked the running BCAT-6 (Binary Colloidal Alloy Test-6)-Phase Separation experiment for camera & flashlight battery charge. The Nikon D2Xs camera with EarthKAM software running with the Intervalometer on SSC-18 (Station Support Computer 18) is taking automated flash photography of Sample 3. [After starting on 11/10, the camera is running for a total of 7 days, taking one photo each hour. Camera battery change and Intervalometer restart is done three times a day. Objective of BCAT-6 Phase Separation: to gain unique insights into how gas and liquid phases separate and come together in microgravity. These fundamental studies on the underlying physics of fluids could provide the understanding needed to enable the development of less expensive, longer shelf-life household products, foods, and medicines.]

Sergey Volkov underwent his 3rd preliminary (predvariteljnaya) ODNT run, assisted by Satoshi Furukawa and ground telemetry support at 3:54am-4:12am EST. [The Chibis run was conducted in the below-the-waist reduced-pressure device (ODNT, US: LBNP/Lower Body Negative Pressure) on the TVIS treadmill. The Chibis provides gravity-simulating stress to the body’s cardiovascular/circulatory system for evaluation of the crewmember’s orthostatic tolerance (e.g., the Gauer-Henry reflex) after his long-term stay in zero-G. Data output includes blood pressure readings. The preparatory training generally consists of first imbibing 150-200 milliliters of water or juice, followed by one cycle of a sequence of progressive regimes of reduced (“negative”) pressure, today set at -25, -30, -35, and -40 mmHg for five min. each, while shifting from foot to foot at 10-12 steps per minute, while wearing a sphygmomanometer to measure blood pressure and the REG SHKO Rheoencephalogram Biomed Cap. The body’s circulatory system interprets the pressure differential between upper and lower body as a gravity-like force pulling the blood (and other liquids) down. Chibis data and biomed cardiovascular readings are recorded. The Chibis suit (not to be confused with the Russian “Pinguin” suit for spring-loaded body compression, or the “Kentavr” anti-g suit worn during reentry) is similar to the U.S. LBNP facility (not a suit) used for the first time on Skylab in 1973/74, although it appears to accomplish its purpose more quickly.]

Satoshi broke out and set up the hardware for the INTEGRATED IMMUNE saliva samplings, to be collected of Mike & himself every other day for six days, scheduled to start tomorrow. [INTEGRATED IMMUNE (Validating Procedures for Monitoring Crew member Immune Function) samples & analyzes participant’s blood, urine, and saliva before, during and after flight for changes related to functions like bone metabolism, oxidative damage and immune function to develop and validate an immune monitoring strategy consistent with operational flight requirements and constraints. The strategy uses both long and short duration crewmembers as study subjects. The saliva is collected in two forms, dry and liquid. The dry samples are collected at intervals during the collection day using a specialized book that contains filter paper. The liquid saliva collections require that the crewmembers soak a piece of cotton inside their mouths and place it in a salivette bag; there are four of the liquid collections during docked operations. The on-orbit blood samples are collected right before undocking and returned to the ground so that analysis can occur with 48 hours of the sampling. This allows assays that quantify the function of different types of white blood cells and other active components of the immune system. Samples are secured in the MELFI (Minus-Eighty Laboratory Freezer for ISS). Also included are entries in a fluid/medications intact log, and a stress-test questionnaire to be filled out by the subject at begin and end. Urine is collected during a 24-hour period, conventionally divided into two twelve-hour phases: morning-evening and evening-morning.]

FE-4 conducted the routine daily servicing of the SOZh system (Environment Control & Life Support System, ECLSS) in the SM. This included the weekly collection of the toilet flush (SP) counter and water supply (SVO) readings for calldown to TsUP-Moscow, as well as the weekly checkup on the Russian POTOK-150MK (150 micron) air filter unit of the SM’s & FGB’s SOGS air revitalization subsystem, gathering weekly data on total operating time & “On” durations for calldown. [SOZh servicing includes checking the ASU toilet facilities, replacement of the KTO & KBO solid waste containers and replacement of EDV-SV waste water and EDV-U urine containers].

At ~2:30pm, Satoshi Furukawa was scheduled for his weekly PFC (Private Family Conference), via S-band/audio and Ku-band/MS-NetMeeting application (which displays the uplinked ground video on an SSC laptop).

The crew worked out with their regular 2-hr physical exercise protocol on the CEVIS cycle ergometer with vibration isolation (FE-5), TVIS treadmill with vibration isolation & stabilization (FE-4/2x), ARED advanced resistive exercise device (CDR, FE-5), and T2/COLBERT advanced treadmill (CDR).

Tasks listed for Sergey Volkov on the Russian discretionary “time permitting” job for today were –

* Continuing the preparation & downlinking of more reportages (written text, photos, videos) for the Roskosmos website to promote Russia’s manned space program (max. file size 500 Mb),

* Another ~30-min. run of the GFI-8 “Uragan” (hurricane) earth-imaging program with the NIKON D3X digital camera with Sigma AF 300-800mm telelens, aiming for the Voronezh area and oil pollution in the Caspian Sea;

* Inspecting & photographing the space behind SM panel 338 (to develop a procedure for installation of the S Ju309 mono unit on Regul-OS work area 3 to replace the SA25-3 device removed in April 2011), and

* Another ~30-min. session for Russia’s EKON Environmental Safety Agency, making observations and taking KPT-3 aerial photography of environmental conditions on Earth using the NIKON D3X camera with the RSK-1 laptop.

Phobos-Grunt Visibility: The ISS crew was notified of viewing/photographing opportunities for the stranded Phobos-Grunt Mars probe from the DC-1 VL-1 and MRM2 windows as it crossed the ISS trajectory last night at 11:06:16pm EST and 11:52pm EST.

No CEO targets uplinked for today.

ISS Orbit (as of this morning, 5:32am EST [= epoch])
* Mean altitude – 387.4 km
* Apogee height – 402.2 km
* Perigee height – 372.6 km
* Period — 92.30 min.
* Inclination (to Equator) — 51.64 deg
* Eccentricity — 0.0021849
* Solar Beta Angle — -69.1 deg (magnitude decreasing)
* Orbits per 24-hr. day — 15.60
* Mean altitude loss in the last 24 hours – 133 m
* Revolutions since FGB/Zarya launch (Nov. 98) — 74,421
* Time in orbit (station) – 4741 days
* Time in orbit (crews, cum.) — 4028 days

Significant Events Ahead (all dates Eastern Time and subject to change):
————–Three-crew operations (Increment 29)————-
11/13/11 — Soyuz TMA-22/28S launch – D.Burbank (CDR-30)/A.Shkaplerov/A.Ivanishin (11:14pm EST)
11/16/11 — Soyuz TMA-22/28S docking (MRM2 “Poisk”) (~12:33am)
————–Six-crew operations————-
11/21/11 — Soyuz TMA-02M/27S undock/landing (End of Increment 29) (~5:57pm/9:25pm)
————–Three-crew operations————-
12/xx/11 — SpaceX Falcon 9/Dragon — (Under Review)
12/21/11 — Soyuz TMA-03M/29S launch – O.Kononenko (CDR-31)/A.Kuipers/D.Pettit — (Target Date)
12/23/11 — Soyuz TMA-03M/29S docking (MRM1) — (Target Date)
————–Six-crew operations—————-
TBD — Progress M-13M/45P undock
TBD — Progress M-14M/46P launch
TBD — Progress M-14M/46P docking (DC-1)
02/29/12 — ATV3 launch readiness
TBD — Soyuz TMA-22/28S undock/landing (End of Increment 30)
————–Three-crew operations————-
03/xx/12 — Soyuz TMA-04M/30S launch – G.Padalka (CDR-32)/J.Acaba/K.Volkov — (Target Date)
04/xx/12 — Soyuz TMA-04M/30S docking (MRM2) — (Target Date)
————–Six-crew operations—————-
05/05/12 — 3R Multipurpose Laboratory Module (MLM) w/ERA – launch on Proton (under review)
05/06/12 — Progress M-14M/46P undock
05/07/12 — 3R Multipurpose Laboratory Module (MLM) – docking (under review)
05/xx/12 — Soyuz TMA-03M/29S undock/landing (End of Increment 31)
————–Three-crew operations————-
05/xx/12 – Soyuz TMA-05M/31S launch – S.Williams (CDR-33)/Y.Malenchenko/A.Hoshide
05/xx/12 – Soyuz TMA-05M/31S docking
————–Six-crew operations—————-
09/xx/12 — Soyuz TMA-04M/30S undock/landing (End of Increment 32)
————–Three-crew operations————-
10/xx/12 — Soyuz TMA-06M/32S launch – K.Ford (CDR-34)/O.Novitskiy/E.Tarelkin
10/xx/12 – Soyuz TMA-06M/32S docking
————–Six-crew operations————-
11/xx/12 — Soyuz TMA-05M/31S undock/landing (End of Increment 33)
————–Three-crew operations————-
11/xx/12 — Soyuz TMA-07M/33S launch – C.Hadfield (CDR-35)/T.Mashburn/R.Romanenko
12/xx/12 – Soyuz TMA-07M/33S docking
————–Six-crew operations————-
03/xx/13 — Soyuz TMA-06M/32S undock/landing (End of Increment 34)
————–Three-crew operations————-
03/xx/13 – Soyuz TMA-08M/34S launch – P.Vinogradov (CDR-36)/C.Cassidy/A.Misurkin
03/xx/13 – Soyuz TMA-08M/34S docking
————–Six-crew operations————-
05/xx/13 – Soyuz TMA-07M/33S undock/landing (End of Increment 35)
————–Three-crew operations————-
05/xx/13 – Soyuz TMA-09M/35S launch – M.Suraev (CDR-37)/K.Nyberg/L.Parmitano
05/xx/13 – Soyuz TMA-09M/35S docking
————–Six-crew operations————-
09/xx/13 – Soyuz TMA-08M/34S undock/landing (End of Increment 36)
————–Three-crew operations————-
09/xx/13 – Soyuz TMA-10M/36S launch – M.Hopkins/TBD (CDR-38)/TBD
09/xx/13 – Soyuz TMA-10M/36S docking
————–Six-crew operations————-
11/xx/13 – Soyuz TMA-09M/35S undock/landing (End of Increment 37)
————–Three-crew operations————-
11/xx/13 – Soyuz TMA-11M/37S launch – K.Wakata (CDR-39)/R.Mastracchio/TBD
11/xx/13 – Soyuz TMA-11M/37S docking
————–Six-crew operations————-
03/xx/14 – Soyuz TMA-10M/36S undock/landing (End of Increment 38)
————–Three-crew operations————-