NATIONAL AERONAUTICS AND SPACE ADMINISTRATION (NASA)
GATEWAY PROGRAM JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION (JOFOC)
FOR THE MINIMAL HABITATION MODULE (MHM)

1. FAR 6.303-2(b)(2) – The nature and/or description of the action being approved:

In August 2016, NASA selected six U. S. companies under the Next Space Technologies for
Exploration Partnerships – 2 (NextSTEP-2) Broad Agency Announcement (BAA),
Appendix A, Habitat Systems to help expand knowledge, commercial capabilities and
opportunities in space by developing full-sized ground prototypes and concepts for deep
space habitats.

NASA currently has a requirement to procure a module (full or partial) to be launched late
calendar year 2023 for the NASA Gateway. In the interest of schedule, economy and
efficiency, the procurement of the module will be pursued as a follow-on to the originally
competitively awarded NextSTEP-2 BAA Appendix A, Habitat Systems studies. This
justification provides the rationale for the following:

  1. NASA’s decision to limit the number of responsible source(s) to one or more of the
    existing contracts already in place via the NextSTEP-2 BAA Appendix A, Habitat
    Systems to further mature requirements and system definition leading to the Design,
    Development, Test & Evaluation (DDT&E) and delivery to NASA of a module for
    the NASA Gateway which must be launched late 2023(See below); and

  2. NASA’s decision, based on review of each NextSTEP-2 contractor’s capabilities, to
    sole source the procurement of the MHM flight unit for the cislunar Gateway to
    Northrop Grumman Innovation Systems (NGIS) as a follow-on to the originally
    competitively awarded NextSTEP-2 BAA Appendix A, Habitat Systems studies,
    Contract NNH15CN76C (See below).

A) Use of existing contracts already in place via the NextSTEP-2 BAA Appendix A,
Habitat Systems:

On December 11, 2017, the Space Policy Directive 1, of the President directed a change in
national space policy that provides for a U. S.-led, integrated program with international
and private sector partners for a human return to the Moon. On March 26, 2019, the
President’s mandate was reinforced by Vice President Pence, Chairman of the National
Space Council, who tasked NASA with landing humans on the Moon’s South Pole by
2024.

On May 30, 2019, NASA issued Synopsis Number: 80JSC019GTWYHAB informing the
public of NASA’s requirement to procure one or more module(s) for the NASA Gateway and
its intent to use one or more existing contracts already in place via the NextSTEP-2 BAA
Appendix A, Habitat Systems in order to meet the Gateway Program schedule.

The NextSTEP-2 Appendix A contractors have completed studies leading to definition of
innovative mission architecture; substantiated their operational concepts; developed and
tested ground prototypes; and demonstrated required core capabilities in multiple
subsystems, including distributed avionics, modular power, redundancy management and
autonomous operations. These efforts have positioned the NextSTEP-2 Appendix A
contractors to expeditiously support the agency mandate to return to the Lunar vicinity and
enable human exploration missions by 2024.

The decision to choose design(s) already matured under NextSTEP-2 Appendix A is made
pursuant to FAR 6.302-1(a)(2)(ii)(A) and (B), which enables the use of other than full and
open competition procedures in cases when the supplies or services required are deemed to
be available from only one or a limited number of responsible source(s) and no other supplies
or services will satisfy agency requirements. Supplies/Services may be deemed to be
available only from the original source for the continued development and production of a
major system or highly specialized equipment, including major components thereof, when it
is likely that award to any other source would result in substantial duplication of cost to the
Government that is not expected to be recovered through competition, or unacceptable delays
in fulfilling the agency’s requirements.

Due to the time and expense required to design and fabricate a human-rated deep space
module, it is necessary for NASA to begin development activity as quickly as possible and be
able to leverage the work already accomplished under Appendix A of the NextSTEP-2 BAA.
Over the past three years, NextSTEP-2 BAA contractors have extensively developed initial
designs and operational concepts for establishing a Gateway station in lunar orbit.

NASA’s schedule analysis has shown that development, fabrication, testing and launch of a
MHM for Gateway using existing assembly lines with minor modifications and use of
existing tooling should take approximately three years. A design at the Critical Design
Review stage (no new technologies, new tooling required) would take four years, while a
design at the System Requirement Review stage (no new technologies) would take five years.
Furthermore, a new full and open competition would cause an additional delay of 12-18
months or more in fulfilling the agency’s requirements.

In order to support the mandate to enable a human landing capability in 2024, the MHM
must be launched in late 2023 to be delivered to Gateway no later than early 2024. The
schedule constraints established by a December 2023 launch dictate that a module be on dock
at Kennedy Space Center in mid-2023 for launch processing and integration. Per NASA’s
schedule analysis, this typical timeline for module production must already be compressed in
order to achieve the 2024 human lunar landing deadline. Given that the NextSTEP-2
contractors advanced designs to a near System Design Review (SDR) fidelity, NASA
determined that it must utilize the existing concepts from the NextSTEP-2 Appendix A and
use the development done to date to minimize the additional design work necessary to
produce a module in time.

In addition, award to any other source may result in substantial duplication of cost to the
Government that is not expected to be recovered through competition. NASA has invested $87M to date plus substantial GFE expenses in partnered activities with the vendors in
advancing these capabilities.

For these reasons, NASA has decided to limit the number of responsible source(s) to one or
more of the existing contracts already in place via the NextSTEP-2 BAA Appendix A.

B) Sole Source of the MHM to NGIS:

The planned Gateway lunar orbiting platform is critical for staging human exploration
missions to the lunar surface by 2024 as mandated by Vice President Pence, Chairman of
the National Space Council. The Gateway platform will include a pressurized habitation
module with environmental control and life support systems to house astronauts during
lunar missions. To accomplish a lunar landing, astronauts aboard an Orion Spacecraft will
launch toward the moon on an SLS rocket, rendezvous with Gateway (with the MHM) in a
lunar orbit, and descend to the lunar surface via a crewed lander by 2024.

In order to meet NASA’s 2024 human lunar landing deadline, NASA examined the existing
NextSTEP-2 contractors’ concepts for deep space habitation modules. As stated in the
synopsis (80JSC019GTWYHAB), not all contractors currently performing services via the
NextSTEP-2 BAA Appendix A, would be selected to receive an award for this next phase
and additional phases. Each contractor’s proposed approach, progress, and capabilities were
reviewed and assessed by NASA for potential use as a MHM. In order to meet the Gateway
Program’s schedule and support the Vice President’s 2024 human lunar landing mandate,
NASA determined it was necessary to continue to work with NGIS for these highly
specialized services. NGIS was the only NextSTEP-2 contractor with a module design and
the production and tooling resources capable of meeting the 2024 deadline.

There are three primary considerations, when combined, which establish NGIS as the
provider uniquely capable of delivering the MHM in time to support the 2024 lunar surface
mission. No other NextStep-2 provider has these existing capabilities which, when
considered collectively, provide the only viable approach to successfully achieving the 2024
lunar mandate:
– Existing Production Capability: Through its NextSTEP work, NGIS developed Gateway
solutions based upon its Cygnus Cargo resupply module. NGIS has an existing production
capability of the Cygnus through a combination of corporate-owned designs and
manufacturing assets, including unique tooling, as well as an exclusive contract with an
established spaceflight module construction firm.

– Critical Subsystem Maturity: NGIS has already advanced design & development for
other critical components adapted to the Cygnus, specifically radial docking ports and body
mounted radiators (BMRs). NGIS and its contractor for spaceflight module construction
have analyzed options to near System Requirements Review (SRR)/ System Definition
Review (SDR) level of maturity for integrating radial docking ports into a Cygnus primary
structure, thereby reducing the schedule risk associated with modified structural
developments. Similarly, Cygnus-specific BMRs are at a CDR level of maturity, with design
and qualification expected to be applicable to use on the MHM.

– Existing LV Fairing Accommodation:
The diameter of the Cygnus module supports the Gateway programmatic requirement to be
compatible with existing commercial launch vehicle providers’ fairings, thereby mitigating
the schedule and cost risk that would be associated with launch providers having to develop
and manufacture new fairings.

Existing Production Capability

NGIS is the only NextSTEP-2 contractor uniquely able to complete design, development and
production of the MHM within the time necessary to launch in late 2023 and get the module
on station in lunar orbit early 2024 using existing launch vehicles. NGIS has an existing,
active pressurized module manufacturing capability via their ongoing Cygnus module
construction subcontractor that has provided experience and lessons learned from
development of 13 Cygnus vehicles to date, refining management and technical interactions
and interchanges. This existing contractual relationship and its associated production
pedigree are critical to timely development progress and problem resolution, which are
substantive mitigations to schedule risk. This production relationship is unique to NGIS
among the NextSTEP-2 vendors, and can be highly leveraged to achieve successful DDT&E
and timely delivery of the MHM.

Critical Subsystem Maturity

The Cygnus module design can be adapted to provide the structural basis for the MHM. In
addition to the existing fundamental design, during the NextSTEP-2 activities NGIS and its
contractor for spaceflight module construction have been designing modifications for
inclusion of radial docking ports which would enable multiple visiting vehicles to attach to
the MHM simultaneously, thus enabling the lunar landing architecture to be implemented
initially with the MHM serving as the sole transfer node for the 2024 mission.

The Gateway module will also have to reject heat generated by its own powered systems.
Given that body mounted radiators are already in development specifically for the Cygnus
module, the development of the critical thermal control subsystem is substantially advanced.
Design modifications to enable BMRs to cover more surface area of an extended Cygnus
structure are readily viable and provide flexibility in the implementation of the Gateway
power and avionics architectures and also reduces schedule risk. These advanced docking
port and thermal development activities further position NGIS as the only NextSTEP-2
contractor with the capability to produce an integrated module to meet the December 2023
launch schedule.

Existing LV Fairing Accommodation

In order to meet the 2024 deadline, NASA must use existing commercial launch vehicles to
transport a MHM to lunar orbit for integration into Gateway in time to support the Vice
President’s mandate. Through the existing manufacturing capability previously described,
NGIS has tooling and manufacturability for production of a module with a diameter that can
be uniquely accommodated by existing Commercial Launch Vehicle fairings, while still
supporting radial docking or externally-mounted hardware. While other common module
diameter sizes could potentially be fabricated with already built tooling, those larger
diameters would not accommodate radial docking ports as required.

Additionally, the smaller diameter of the NGIS module enables other externally mounted
capabilities, including batteries, communication antennae, and payloads to be incorporated
upon launch and available for the initial mission. These capabilities uniquely establish a
minimum risk development posture for supplying the initial docking and habitable transfer
capability necessary to support lunar operations in 2024.

Lastly, a new full and open competition would cause an additional delay of 12-18 months or
more in fulfilling the agency’s requirements.

2. FAR 6.303-2(b)(3) – A description of the supplies or services required, to meet the
Agency’s needs (including the estimated value):

NASA has a requirement to procure a MHM for the NASA Gateway that will meet the
Gateway Program schedule and support the President’s mandate through the U. S. Space
Council to return to the Lunar vicinity, enable human exploration missions by 2024.

The required MHM must be a functional pressurized volume providing sufficient command,
control & data handling capabilities, energy storage and power distribution, thermal control,
communications and tracking capabilities, environmental control and life support systems to
augment the Orion spacecraft and support a crew of four for at least 30 days; two axial and
up to two radial docking ports; stowage volume; and utilization capabilities.

Of the NextSTEP-2 contractors, NASA determined that only NGIS could complete the work
in time for a December 2023 launch because of their existing production capability in
partnership with its spaceflight module construction contractor, their advancement of critical
docking port and thermal control system designs directly applicable to the existing Cygnus
primary structure design, and the capability of their module to be launched while
encapsulated within an existing commercial launch vehicle fairing. The combination of these
development activities and existing capabilities establish NGIS as uniquely qualified to
produce the MHM within the required schedule.

This effort is anticipated to have a 5-year base period (September 1, 2019 – August 31, 2024)
to allow for delivery of the module to the Gateway; and two, 1-year options (September 1,
2024 – August 31, 2025) and (September 1, 2025 – August 31, 2026) for checkout of the
module’s systems and continued contractor support for autonomous and human-tended
operations, including the first lunar landing sortie from Gateway.

The total value of this effort is estimated to be approximately [REDACTED] for the MHM.

3. FAR 6.303-2(b)(4) – An identification of the statutory authority permitting other than
full and open competition:

The statutory authority for this JOFOC is 10 U. S. C. 2304(c)(1) as implemented by Federal
Acquisition Regulation (FAR) 6.302-1(a)(2)(ii)(A) and (B), which enables the use of other
than full and open competition procedures in cases when the supplies or services required are
deemed to be available from only one or a limited number of responsible source(s) and no  other supplies or services will satisfy agency requirements. Supplies/Services may be
deemed to be available only from the original source for the continued development and
production of a major system or highly specialized equipment, including major components
thereof, when it is likely that award to any other source would result in substantial
duplication of cost to the Government that is not expected to be recovered through
competition, or unacceptable delays in fulfilling the agency’s requirements.

As previously stated, awarding to any other source would result in substantial duplication of
cost to the Government that is not expected to be recovered through competition. NASA has
invested over $18M with NGIS in developing its unique module habitation
concepts. Additionally, NGIS has advanced their uniquely proposed designs to a near
System Definition Review (SDR) fidelity which, if it were not leveraged, would result in
unacceptable delays in fulfilling the agency’s requirement.

When it comes to the selection of NGIS for the MHM, per NASA’s analysis, NGIS is the
only contractor that can provide the MHM essential to meeting the minimum Gateway
habitation requirements while meeting the 2024 lunar landing schedule. Conducting a new
full and open competition to enable the consideration of any other contractor, would cause
unacceptable delays of at least 12-18 months. Similarly, conducting additional competition
among the NextSTEP-2 contractors would induce unacceptable delay of up to 6 months.
Beyond the procurement delay, an additional delay of 6-12 months or more would be
required to reach sufficient design maturity to begin fabricating the tooling necessary to then
manufacture the module. Rushing the design and development processes to meet schedule
introduces unacceptable risk that the resultant module would not meet the minimum
requirements for astronaut habitation needed to support the 2024 lunar landing mission.

4. FAR 6.303-2(b)(5)&(9) – A demonstration that the proposed contractor’s unique
qualifications or the nature of the acquisition requires use of the authority cited and
any other facts supporting the use of other than full and open competition such as:

NASA has a requirement to procure a MHM for the NASA Gateway that will meet the
Gateway Program schedule and support the agency mandate to return to the Lunar vicinity,
enable human exploration missions by 2024.

The required MHM must be a functional pressurized volume providing sufficient command,
control & data handling capabilities, energy storage and power distribution, thermal control,
communications and tracking capabilities, environmental control and life support systems to
augment the Orion spacecraft and support a crew of four for at least 30 days; two axial and
up to two radial docking ports; stowage volume; and utilization capabilities. The MHM will
be launched in Q4 CY23. The module must be capable of being launched using a
commercial launch vehicle and therefore must be sized to fit within existing fairing envelope
dimensions.

NGIS is uniquely positioned to deliver the required module within the schedule and technical
constraints identified as demonstrated below and discussed more fully in Section 1.B.

NGIS:

  • Has an existing, active pressurized module primary structure manufacturing capability

    via their ongoing Cygnus module production that can be adapted to provide the
    structural basis for the MHM, uniquely providing a capability to meet the December
    2023 launch schedule necessary to support Lunar surface operations in 2024.

  • Has existing tooling and manufacturability for development of a module with a diameter
    that can be accommodated by existing CLV fairings (Cygnus diameter is 3m), while still
    supporting radial docking or externally-mounted hardware, uniquely establishing a
    minimum risk development posture for supplying the initial docking and habitable
    transfer capability necessary to support lunar operations in 2024.

  • Has developed and demonstrated habitat module concept designs through NextSTEP
    Phase 1 and 2 approaching SRR and SDR maturity and in some areas, beyond SRR/SDR
    fidelity; enabling them to meet Gateway schedule requirements that are responsive to
    Agency mandates.

5. FAR 6.303-2(b)(6) – A description of the efforts made to ensure that offers are solicited
from as many potential sources as practicable, including whether a notice was or will be
publicized as required by Subpart 5.2 and, if not, which exception under 5.202 applies:

Pursuant to FAR 5.201(b)(1); Synopses of Proposed Contract Actions, General; the
proposed contract action was synopsized via the Government Point of Entry (GPE). The
website for the GPE is the Federal Business Opportunities (FedBizOpps) website is located
at https://www.fbo.gov.

On May 30, 2019, a Special Notice was posted to the GPE, which provided notification of
the Government’s requirement to procure one or more module(s) (full or partial) for the
NASA Gateway. The Special Notice also included a statement that interested organizations
may submit their capabilities and qualifications to perform the effort on schedule and
without resulting in substantial duplication of cost to the government.

The Special Notice stated the Government’s intent to execute Justification(s) for Other than
Full and Open Competition to limit the number of responsible source(s) to one or more of
those sources already engaged in the NextSTEP-2 BAA Appendix A, Habitat Systems to
further mature requirements and system definition leading to DDT&E and delivery to
NASA of one or more module(s) (full or partial) for the NASA Gateway.

The NextSTEP-2 Appendix A contractors’ concepts were assessed for potential use as a
Minimal Habitat. Northrop Grumman was the only contractor with concepts and the
development and production capability that met both requirements and schedule.

6. FAR 6.303-2(b)(7) – A determination by the contracting officer that the anticipated cost
to the Government will be fair and reasonable:

Upon approval of this justification, a Request for Proposal will be issued to NGIS. NGIS
will submit a proposal that will be evaluated and negotiated by the Government. A cost and
price analysis will be performed in accordance with FAR 15.404-1(a) (3), Proposal Analysis Techniques, to verify that the overall price is fair and reasonable. Also, in accordance with
FAR 15.403-4, Requiring Certified Cost or Pricing Data, NGIS will be required to execute a
Certificate of Current Cost or Pricing Data when a fair and reasonable price based upon
NGIS proposal is agreed upon.

  1. FAR 6.303-2(b)(8) – Description of the market survey conducted, and the results, or a
    statement of the reasons a market survey was not conducted:

    As part of our market survey, a synopsis was issued on May 30, 2019. The synopsis closed
    on June 13, 2019, and the Government did not receive any qualification and capability
    statements.

  2. FAR6.303-2(b)(10)–Alistingofthesources,ifany,thatexpressedaninterestinwriting
    in the acquisition:

    See item #7

  3. FAR 6.303-2(b)(11) – A statement of actions, if any, the agency may take to remove or
    overcome any barriers to competition before any subsequent acquisition for the
    supplies or services required:

    Follow-on acquisitions are undetermined at this time. 

 

 