Status Report

NASA Expendable Launch Vehicle Status Report 4 August 2006

By SpaceRef Editor
August 5, 2006
Filed under , ,

Mission: STEREO (Solar Terrestrial Relations Observatory)
Launch Pad: 17-B, Cape Canaveral Air Force Station
Launch Vehicle: Boeing Delta II
Launch Date: Aug. 31, 2006
Launch Time: 3:12:24 or 4:20:28 p.m. EDT

At Launch Complex 17, the second stage of the Boeing Delta II was de-stacked on Tuesday and taken to the nearby High-Pressure Test Facility. The planned precautionary leak test has been completed. No leak was observed. The second stage will be returned to the launch pad on Saturday and mated again with the Delta first stage.

In the Hazardous Processing Facility clean room, the two STEREO observatories are scheduled to be stacked on Aug. 9 in preparation for spin test activities. These are planned to begin on Aug. 11. The integrated STEREO payload will then be mated to the upper stage booster on Aug. 16 and transported to Pad 17-B on Aug. 19 for integration with the Delta II.

For previous expendable launch vehicle processing status reports, visit:

http://www.nasa.gov/centers/kennedy/launchingrockets/status/2006

SpaceRef staff editor.