TsUP [Mission Control Center]

TsNIIMash [Central Scientific Research Machine Building Institute]

Rosaviakosmos [Russian Aviation and Space Agency]

Moscow, Russia

Press release: March 19, 2001, 09:00 (Moscow time) [06:00 UTC]

In accordance with the de-orbit plan the OC [Orbital Complex] “Mir” is
drifting in a waiting mode, its deceleration continues in upper layers
of atmosphere.

A routine check out of the OC “Mir” onboard systems was performed during
the previous day, its trajectory parametres registered. Telemetry data
and the core block TV displays are used to control MCS, thermal mode,
the station pressure integrity.

The data received and processed at MCC confirm the complex “Mir” readiness
for final stage operations.

The next status report will be issued on March 20.

Trajectory report No 60
19.03.2001 (OC “MIR”) Date: 19.03.2001

  • Flight orbitÝnumber (day): 86267(01)

  • Orbit period (in min): 88.995

  • Mean orbit altitude (km): 227.9

  • Daily average altitude decay (km): 3.0

  • Beta angle, i.e. the angle of the
    Sun vector to the orbital plane (in degrees): +52.1

  • Duration of daylight (min): 57.9

  • Solar and geomagnetic activity current parameters:

    solar F10.7 flux: 135

    geomagnetic index Ap: 8

    F10.7 <= 100 -- low level;

    100 < F10.7 < 150 -- medium level;

    F10.7 >= 150 — high level

  • Time of altitude Hav ~ 220 km
    Dynamic operations are scheduled to start on:21.03.2001 +2 days

  • Re-entry prediction with consideration of
    15% deviation from solar flux activity value: 28.03.2001 +2 days / -1 days

  • Date of the orbit parameters calculations: 19.03.2001

  • Renewed information is expected on 20.03.2001 at 01.00 p.m. DMT.