Mir Status Report 18 Mar 2001
TsUP [Mission Control Center]
TsNIIMash [Central Scientific Research Machine Building Institute]
Rosaviakosmos [Russian Aviation and Space Agency]
Moscow, Russia
Press release: March 18, 2001, 09:00 (Moscow time) [06:00 UTC]
The operation with OC [Orbital Complex] “Mir” scheduled for March 17 is
complete.
The recent telemetry data confirmed the OC “Mir” remains pressurized, the
thermal condition is normal, continues deceleration in the upper atmosphere.
The next status report will be issued on March 19.
Trajectory report No 59 18.03.2001 (OC “MIR”) Date: 18.03.2001
Sun vector to the orbital plane (in degrees): +51.7
solar F10.7 flux: 130
geomagnetic index Ap: 8
F10.7 <= 100 -- low level;
100 < F10.7 < 150 -- medium level;
F10.7 >= 150 — high level
Dynamic operations are scheduled to start on: 21.03.2001 +2 days
15% deviation from solar flux activity value: 28.03.2001 +3 days / -2 days