Status Report

James Webb Space Telescope: Opportunity Nears to Provide Additional Assurance That Project Can Meet New Cost and Schedule Commitments

By SpaceRef Editor
March 26, 2019
Filed under , ,

What GAO Found 

In June 2018, the National Aeronautics and Space Administration (NASA) revised the cost and schedule commitments for the James Webb Space Telescope (JWST) to reflect known technical challenges, as well as provide additional time to address unanticipated challenges. For example, the revised launch readiness date of March 2021 included 5.5 months to address a design issue for the cover of the sunshield (see image). The purpose of the sunshield is to protect the telescope’s mirrors and instruments from the sun’s heat. NASA found that hardware on the cover came loose during testing in April 2018. The new cost estimate of $9.7 billion is driven by the schedule extension, which requires keeping the contractor’s workforce on board longer than expected.

Before the project enters its final phase of integration and test, it must conduct a review to determine if it can launch within its cost and schedule commitments. As part of this review, the project is not required to update its joint cost and schedule confidence level analysis—an analysis that provides the probability the project can meet its cost and schedule commitments—but government and industry cost and schedule experts have found it is a best practice to do so. Such analysis would provide NASA officials with better information to support decisions on allocating resources, especially in light of the project’s recent cost and schedule growth.

NASA has taken steps to improve oversight and performance of JWST, and identified the JWST project manager as responsible for monitoring the continued implementation of these changes. Examples of recent changes include increasing on-site presence at the contractor facility and conducting comprehensive audits of design processes. Sustaining focus on these changes through launch will be important if schedule pressures arise later and because of past challenges with communications. GAO will follow up on the project’s monitoring of these improvements in future reviews.

Full report

SpaceRef staff editor.