ISS Increment 2 and 3 Management Status Report
International Space Station- Increment 2 Management
Accomplishments:
Sta ge 6A priorities.
except for 5 items that were deferred: MACE
(mass stora ge device checkout), CHeCS rack
and equipment checkout, Inte grated checkout
of PL MDM, PEHG, and APS, Install/ activate
HRF Rack- 1, misc. payload activities.
date for Expedition 2 priorities.
Plans:
Anomaly Resolution Team meetings.
Pro gram decision tree for what is required
to commit to Fli ght 7A.
IDRD Priorities.
Issues and Concerns:
resolution. Assessing impacts to increment
scheduling and requirements.
International Space Station- Increment 3 Management
Accomplishments:
IDRD PP3 Rev. B- 1 (CR 5241)
TCM [5/ 4]
launch slip from 11/ 1/ 01 to 11/ 29/ 01
5P, 4R, and 6P
from 7A. 1 (planned for EVA by Expedition 3)
Plans :
On- orbit Maintenance Plan
PEEK units for ISS- 3
Sims [5/ 15]
Issues and Concerns: