International Space Station-Increment 6 Management 9 Apr 2003
Source: ISS Monthly Program Review, Vol. 131, 11 April 2003
Accomplishments:
Baselined CSRD Rev. A (EVA #2 & Increment extension requirements)
Completed RS version 7.01 s/w update [18 Mar 03]
Conducted Robotics operations
- Stage EVA #2 viewing platform & post-EVA configuration survey
- Completion of On-orbit Check-out Requirements [11 Apr 03]
Performed MTL PPA failure troubleshooting & replaced MTL PPA with only on-board spare [18 Apr 03]
- ITCS operating in dual loop mode for 2 weeks to observe MTL PPA performance [9 Apr 03]
Conducted Stage 11A EVA #2 [8 Apr 03, 6:26]
- CMG cable reconfig
- Lab HX SPD installation
- RBVM thermal cover re-installation
- MT RPCM replacement
- ATA cap retrieval
- Get-aheads: CETA light & stanchion, S0/S1 & S0/P1 BBC demate, NTA cable inspection, misc. tool retrievals
Conducted RS & U.S. solar array efficiency tests [3/9 Apr03]
Complete Progress-based reboost/Soyuz phasing burns [4/10 Apr 03]
Performed defibrillator troubleshooting [11 Apr 03]
Payload operations: additional FOOT run, EVA-related PuFF data takes, EVARM badge readings; EarthKAM
- Completed MSG troubleshooting & resumed nominal ops
- Began InSPACE processing [31 Mar 03]
Plans:
Continue InSPACE sample processing
Attempt ARCTIC freezer repair [TBD]
Continue crew rotation preparation (TMA descent study, medical operations, pre-pack, etc.)
Continue post-landing planning
Conduct 5S/6S joint operations & return Expedition 6 crew on 5S [28 April – 4 May]
Issues/Concerns:
Crowded timeline between now and 6S arrival