International Space Station-Increment 2, 3, and 4 Management Status 10 Aug 2001
Note: excerpt from 10 August 2001: Felicity Vol. 72, NASA JSC [2.9 Mb Acrobat]
International Space Station-Increment 2 Management
Accomplishments:
This was a crew request to insure appropriate
subjects included debriefing comments by
all crew members since Usachev returns to
Moscow at L+ 10 days. Being conducted during
crew pre-sleep time per their request.
real-time updates to IDRD priorities. Should
result in more timely Russian concurrences.
released for review via CHIT.
Payloads to be official responder instead of
making their inputs through IMC.
Sta ge objectives for this stage by 7A..
the Increment 2 science objectives will be
Accomplished by 7A.1 (one payload failed)
Plans:
for crew. This includes debriefings, rehab,
medical, travel requirements, etc.
Working to identify Russian contacts
so that post-flight planning is a multilateral
process. Coordination with CSA in place.
Issues and Concerns:
ensure all requirements are identified and
prioritized since crew will be focused on
preparations for handover and return.
International Space Station-Increment 3 Management
Accomplishments:
(CR 5679) [6/29]
contingency back-up for 7A.1 SRMS-assisted tasks
Russian vehicle & EVA plan [7/2]
Plans:
Flight 7A. 1 [7/13]
CR w/updated 7A. 1 Sta ge requirements,
revised crew time allocations, OBT, etc.
On-orbit Maintenance Plan [7/19]
RSC-Energia [7/13]
Issues and Concerns:
International Space Station-Increment 4 Management
Accomplishments:
July 26, 2001
UF-1 SSCN 5735 Approved July 19 & August 2, 2001
Approved August 2, 2001
agreement to move 4S launch, 3S undock dates pending
UF-2 launch date
Plans:
August 27, 2001
August 31, 2001
2001
Issues and Concerns:
and stage, including possible Flt EVA (BMRRM)
proposal for flight 8A assembly tasks