Increment 2,3, and 4 Management Reports

By SpaceRef Editor
April 17, 2001
Filed under , ,

Increment 2 Management

Accomplishments:

  • IDRD CR opened to updated launch date
    chan ges and flight 6A through Stage 7A.
  • Planning TIM completed with Russians.
  • Accepted Russian proposed chan ges in 1S
    relocation, 4P and 5P launch date chan ges
  • Completed 6A/ 2S/ 4P SORR
  • Confirmed available food on- board will last
    throu gh May 29 without resupply

    Plans:

  • Update Sta ge 5A. 1 through 7A priorities
    based on time remaining and flight schedule
    changes
  • Develop metrics to keep requirements owners
    better informed of progress during stage
  • Improve reporting process of daily reports

    Issues and Concerns:

  • There is insufficient crew time remaining in
    Sta ge 5A. 1 to accomplish all requirements.
    Work is in pro gress to replan the remainder
    of the Sta ge. Only tasks required to support
    the 3P, 1S, and 6A vehicle operations will
    be scheduled. All other tasks will be deferred
    to Stage 6A. Deferred tasks include US and
    Russian payload operations, maintenance,
    SDTOs and systems checkouts.
  • We will be gin a process improvement effort
    on 4/9 focused on determining what can
    be accomplished during the remainder of
    this increment, better involvin g customers in
    the planning process both during the IDRD
    planning preflight and realtime, better involving
    the Program in the daily/ weekly planning
    process, and improving our estimates of
    available crew time for the IDRD allocations.

    Increment 3 Management

    Accomplishments:

  • Completed 2 week Increment Plannin g TIM
  • Completed IDRD PP3 Rev. B- 1 work
    (deferred from MIOCB agenda pending
    resolution of crew time allocations)
  • Completed 7A. 1 FOR/ ISS- 3 IOR (product
    review only)
  • Released IDRD PP3 Rev. B- 2 (4/ 6)
  • Includes installation of Node to Airlock
    Hatch Window as ISS- 3 task

    Plans :

  • Conduct IDRD PP3 Rev. B- 2 TCM (4/ 30)
  • Conduct FOR/ IOR outbrief to MIOCB (4/ 19)
  • Schedule Increment 3 IOR (ISSP review)
  • Update IDRD PP3 Annex 2, On- orbit
    Maintenance Plan (U/ R)

    Issues and Concerns :

  • Potential changes in Increment launch &
    return dates
  • Expedition 3 EVA vs. utilization resources

    Increment 4 Management

    Accomplishments:

  • IDRD PP3 SSCN 5241 Launch date
    updates in signature cycle
    – IDRD PP# SSCN 5349 Flight 8A
    requirement updates approved
  • Increment 4 IORR completed April 6
    Plans :
  • IDRD PP3 SSCN to be released April 9,
    TCM April 30; update Payload, Flight
    UF- 1, and Flight UF- 2 Requirements
  • Reconcile Increment 4 crew time
    requirements and utilization availability

    Issues and Concerns :

  • Russian EVA tasks, EVA utilization
    resource accounting and EVA
    implementation
  • Continued definition of Increment 4 tasks
    and crew consumables planning