Status Report

Expected Hubble Space Telescope Science Lifetime After SM4

By SpaceRef Editor
July 31, 2003
Filed under , ,

Expected HST Science Lifetime After SM4

HST Program Office


NASA/Goddard Space Flight Center

July 21, 2003

Introduction

The HST mission is currently planned to continue to the year 2010, and final HST
servicing will occur in Servicing Mission 4 (SM4), which is expected to be launched
sometime in 2005. It cannot be guaranteed that HST science operations will continue all
the way to 2010 without further servicing. The principal factors that affect the lifetime of
HST and the duration of its science capabilities are addressed in this document. These
four factors are:

  • Health of spacecraft systems and their failure probabilities
  • Likelihood of scientific instrument failures
  • Decay of HST’s orbit
  • Degradation of the telescope’s optics

Each of these is discussed below.

Spacecraft Health and Failure Probabilities

The HST science operations depend upon a healthy, reliable and efficient spacecraft.
HST hardware subsystems have significant redundancy. However, hardware failures may
reduce or eliminate redundancy to the point where additional failure can lead to the loss
of function and ultimately to the loss of the science mission.

Maintaining HST spacecraft health and safety is the highest priority task for the HST
Program. Spacecraft subsystem performance is continually monitored. One of the tools
used to forecast HST spacecraft health is the HST Reliability Model. This tool is
extremely useful in planning servicing mission strategies, payload content and priorities.
This model has been reviewed and validated by the HST Independent Review Team.

The Aerospace Corporation developed and maintains the HST Reliability Model for the
HST Program. It encompasses all the spacecraft subsystems with the exception of the
scientific instruments. The model takes into account hardware redundancies and the
regularly updated box-level failure rates. The HST Reliability Model is described in the
Aerospace Corporation report, “Hubble Space Telescope Reliability Assessment, July
2002 Model,” Aerospace Report No. TOR-2003(2154)-2352, dated November 21, 2002,
which will be made available upon request.

It should be noted that the modeling of gyroscope failure probabilities is statistically
stronger than has been possible for other spacecraft components. It is based on the
performance histories, both in ground testing and in flight, of over 90 similar gyroscopes
across many programs. The gyroscope analysis includes both random failures and
physical wear-out, as represented by a Weibull function.

The most recent HST Reliability Model results are as follows.

Probability of continued science operations prior to SM4

Prior to SM4, the model indicates that the reliability of the HST gyroscopes dominate
overall system reliability. Three gyroscopes are required to perform HST science
operations. Of the six gyroscopes on board HST, four are currently functional
(Gyroscopes 1, 2, 4, and 6) and two have failed (Gyroscopes 3 and 5). Following the
failure of Gyroscope #3 in late April 2003, Aerospace recalculated the probability of 3
functional gyroscopes versus time from a time reference beginning July 1, 2003. The
results are shown in the Figure 1. Given the current SM4 launch date baseline of May 5,
2005, the probability of 3 or more functional gyroscopes up through SM4 is
approximately 70 percent. However, the probability of 3 functional gyroscopes decreases
rapidly for a launch date after May 2005. As can be seen in the figure, the probability of
3 functional gyroscopes is approximately 50 percent as of December 1, 2005, and only 30
percent as of July 1, 2006.

hst

The HST Program models overall spacecraft subsystem reliability as a function of time.
The reliability predictions are recalculated based upon the successful completion of a
servicing mission. The model is updated with the assumption that full redundancy will
be restored to the HST spacecraft hardware during Servicing Mission 4, e.g., 6 functional
gyroscopes are restored. The reliability projections are a function of time elapsed
following a servicing mission, and thus are independent of a specific launch date. The
overall system-level curve, shown in Figure 2, is constructed from the product of the
values of reliability versus time for 51 individual subsystems. The gyroscopes comprise
only one element of this calculation.

hst

The model forecasts that 5 years after Servicing Mission 4, the HST system-level
probability for continued science operations is 30 percent. Thus, given the current launch
date baseline of May 5, 2005, the formal probability of continuous science operations
through May 2010 is 30 percent.
Further, the likelihood of continuous science
operations through May 2011 is formally only 18 percent. However, the situation may
not be quite so dire. The model predictions are conservative in two ways. First, an
individual part failure is assumed to cause loss of function for the hardware component
modeled. Components may still function at some level in spite of a single part failure.
Secondly, loss of hardware functionality may be mitigated by workarounds, e.g., added
flight software functionality to overcome the hardware problem. It is simply not possible
in advance of a failure to evaluate how overly-pessimistic the model predictions might
be.

It is of interest to consider the historical record of the durations between Hubble servicing
missions, vis a vis cessation of science operations.

  • Launch (4/90) to SM1 (12/93) – 44 months
  • SM1 to SM2 (2/97) – 38 months
  • SM2 to SM3A (12/99) – 34 months (loss of science operations 11/99)
  • SM3A to SM3B (3/02) – 27 months
  • SM3B to SM4 (~5/05) – >= 38 months

Only one episode of cessation of science operations has occurred, for approximately six
weeks prior to the launch of SM3A, due to gyroscope failures. Currently the Pointing
Control System requires 3 working gyroscopes. Less than 3 gyroscopes leads to HST
entering “Zero-Gyro Safemode”, as happened just before SM3A. The HST Program is
actively planning the potential implementation of a 2-gyro mode for science operations,
that would enable continued science operations, with some loss or degradation of
observing capabilities, for approximately 12 to 15 additional months.

The HST Reliability Model prediction shown in Figure 2 is a generic, “Time since last
Servicing Mission,” curve that assumes full spacecraft redundancy has been restored as
an outcome of the servicing mission. The prediction is applicable not only to SM4 but
also to any Servicing Mission beyond SM4.

Loss of Scientific Instrument Capabilities

Hubble’s scientific instruments are each designed for a five-year operational lifetime in
orbit. Historically, they have lasted considerably longer than that. Only one instrument,
the Goddard High Resolution Spectrograph (GHRS), has suffered an electrical or
mechanical failure that left it completely inoperable. That failure occurred in 1997, just a
few weeks before the GHRS was to be removed from Hubble during the second servicing
mission. The GHRS was one of the original five instruments launched on Hubble in April
1990. After about two years of operation, GHRS lost a portion of its observing
capabilities, but a simple repair by the astronauts restored these during Servicing Mission
1 (SM1) in 1993.

The Near Infrared Camera and Multi-Object Spectrometer (NICMOS) was originally
designed to be cooled by a block of solid nitrogen ice, with an expected lifetime of about
four years. A thermal short in the instrument reduced its “first life” to about 22 months.
However, during Servicing Mission 3B (SM3B) in March 2002, astronauts installed a
newly designed mechanical cooling system and the instrument’s science operations were
resumed (with a 30-50% improvement in sensitivity).

The Space Telescope Imaging Spectrograph was launched along with NICMOS in
Servicing Mission 2 (SM2), February 1997. In the summer of 2001 Side 1 of STIS’
electronics failed irretrievably and it is currently operating on its redundant Side 2. Thus,
even with a significant electronics failure, STIS continues to operate nearly two years
beyond its design lifetime.

The current record holder for longevity among HST instruments is the Wide Field and
Planetary Camera 2 (WFPC2), which has operated without significant failures for nearly
ten years, since its launch in December 2003. Scientifically, it has been superseded by the
Advanced Camera for Surveys (ACS) and will be replaced by Wide Field Camera 3
(WFC3) during Servicing Mission 4 (SM4) in 2005.

At the conclusion of SM4, Hubble’s complement of scientific instruments will consist of
two spectrographs and three cameras (as well as a Fine Guidance Sensor useful for
astrometry). Although there is some overlap of function, as a general rule these
instruments are complementary to each other in their designs. The new Cosmic Origins
Spectrograph (COS) provides some backup to STIS. However, it does not replicate STIS’
capabilities for long-slit imaging spectroscopy, needed for the detection of massive black
holes in galactic nuclei, nor for very high-resolution spectroscopy required for
measurements of chemical abundances in the interstellar gas, for example. The COS is
purely an ultraviolet spectrograph and does not provide a backup to STIS’ coverage from
300 to 1000 nm. The new WFC3 will supplant NICMOS for most near-infrared imaging,
and will complement ACS by providing Hubble’s first wide field, high sensitivity
imaging capability at near-ultraviolet wavelengths. The WFC3 provides some backup to
ACS for visible light imaging, but is not as sensitive as ACS at the red wavelengths of
interest for studies of galaxy evolution.

The lifetimes of WFC3 and COS should extend to 2010. Thus, in 2010 we would expect
Hubble still to have powerful instrumentation both for ultraviolet spectroscopy to very
deep levels of sensitivity and for high-resolution, wide-field imaging spanning the range
200 – 1700 nm. The ACS will be about two years beyond its design lifetime in 2010, but
can reasonably be expected still to be in operation. Its CCD detectors will have suffered
significant levels of degradation in both charge-transfer efficiency and growth of the
population of unusable “hot pixels” to about 6%. However, these signs of “aging”
potentially affect only a sub-set of ACS science and there likely will be operational
approaches to mitigating them. Mechanical cooling systems such as the one now cooling
NICMOS have demonstrated lifetimes of over a decade in ground testing. The lifelimiting
element for NICMOS is likely to be the Power Conversion Electronics for the
cryocooler that provides power to the microturbines. This subsystem is expected to have
a 9% probability of failure after five years of operation. The near-infrared channel of
WFC3 will supplant most of NICMOS’ science capabilities. We have no way of
predicting STIS’ longevity, as it operates on its remaining redundant electronics. It could
fail tomorrow, or it could last many additional years.

Orbital Decay

HST science lifetime could potentially be limited by HST spacecraft orbital decay.
Long-term orbit decay predictions are developed based on atmospheric models and solar
flux predictions. All contributing combinations of solar flux strength and timing are run
in order to bound the orbit decay predictions from a best case atmosphere to a worst case
(“unkind”) atmosphere. The predictions also consider the effects of Space Shuttle re-boost during HST Servicing Missions. Figure 3 shows the model results for a worst case,
2-sigma high solar cycle (Cycle 24), followed by an early Cycle 25 of average intensity.
Figure 3 depicts four curves for various shuttle re-boost scenarios. For the case of no
further HST re-boost in any future servicing mission, the prediction is that HST will reenter
the Earth’s atmosphere in late 2013 or early 2014. The HST science program will
cease approximately one year prior to re-entry due to loss of the precise attitude control
capability required for science observing, as the atmospheric drag increases. The earliest
expected end of the HST science program due to orbital decay is thus late 2012
.
Further information about this topic is contained in the accompanying Hubble Fact Sheet,
entitled “HST Orbit Decay and Shuttle Re-boost.”

hst

Degradation of Primary Optics

Degradation of the HST primary optics could potentially degrade the scientific
performance of the observatory. Contaminants on the primary or secondary mirror, or
physical degradation of the mirror surfaces can result in loss of sensitivity or changes in
the properties of stellar or other point-source images. To date, there is no evidence of any
loss of throughput of the telescope at the level of uncertainty of the measurements (3-
5%), nor is there any evidence of changes in the point spread function over many years,
resulting, for example, from increased wide-angle scattering due to pitting of the mirror
surfaces. More details are contained in the accompanying Hubble Fact Sheet, entitled
“Degradation of Primary Optics.”

Summary

HST science lifetime is limited by the four factors described above. The health of the
HST spacecraft is of most importance in achieving continued science operations through
2010. Even with the servicing of HST in SM4, the goal of meeting science operations
through 2010 will likely fall short. In considering science operations beyond 2010,
spacecraft health continues to be a major factor, and potentially orbital decay can affect
the longevity of HST science. To overcome this, a Servicing Mission in the 2009 to 2010
timeframe that includes a re-boost activity would be required. With such a servicing
mission, the HST science lifetime could be expected to continue into the 2014 to 2015
timeframe.

SpaceRef staff editor.