The EHB met at JSC on May 30, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:

EVA Project Office


Hardware Development


Integration and Operations


Astronaut Office


Engineering Directorate


Crew & Thermal Systems Division


EVA and Spacesuit Systems


EVA, Robotics, & Crew Systems


SR&QA


FCE/EVA


Hamilton Sundstrand Windsor Locks (HSWL) via telecon


Hamilton Sundstrand Management Services


USA


Lockheed

EHB Board members from the following organizations participated:

XA/Chairman, XA/Secretary, XA/Tools and Crew Aids, XA/EMU, XA/Integration and Operations, CB/Astronaut Office, DX32/EVA Task Group,XA/Business Team, EA/Engineering, EC5/EVA GFE, MV5/FCE, and NA/SR&QA.

The following items were presented:

  1. Hardware Integration Schedule XA/Barbara Counts


The schedule is currently under review. More information will be available by the middle of June. As of today, 7A and 7A.1 are both tracking to the same launch date.

  1. PRACA Status NS43/Terry Miller


Twelve A total of fourteen (14) FIAR’s are open for EVA hardware and are shown by flight as follows:

STS-100 (6A) 0


STS-104 (7A) 60

STS-105 (7A.1) 94


STS-109 (HST) 14


STS-108 (UF1) 13

Past due FIAR’s were statused as follows:

JSCEC0853F — Bayonet Probe. STS-92 and STS-98 anomaly reported by crewmember — unsatisfactory fit (tight fit) of bayonet probes to bayonet receptacles.

Final is in signature loop.

BFCE029F105 — PGT. Pistol Grip Tool chatter.


USA had action to take the unit back to Swales. USA/Ernest Sanchez is to contact the Chairman with an update.


JSCEC0851 — General Purpose Cutter (GPC). GPC handle does not lock with torque spec of 10-40 in/lbs., measured 6.6 in/lbs.


EC5/Roger Schwarz reported that the handle has been built up and is in thermal testing. If test results are satisfactory, a CR to roll the dash number will be brought forward. New ECD 6/13/01.


JSCEC0860 — BRT. BRT will not stabilize after tensioning.


No root cause has been found. EC5/Roger Schwarz will discuss with the SSM, Gary Nickel. New ECD 6/13/01.


JSCEC0867 — HSBC. Damaged EVA locking pin on HSBC.


USA is updating PIA procedures. A CARD change will be submitted. New ECD 6/27/01.


JSCEC0874 — _" x _" T-Handle. STS-100 anomaly — sticky actuation of ball.


Hardware is not back from 6A. Will do evaluation once hardware returns. An interim is in place for 7A. New ECD 7/11/01.


JSCEC0873 — Retracting End Effector. Anchor pin found loose inside of the spool pack assembly.


Two more units are being disassembled. Will gather data points and validate difference between them and failed unit. New ECD 6/27/01.

No new FIAR’s were reported.No new FIAR’s were reported.






No FIAR’s are open for STS-100.






No FIAR’s are open for STS-104 (7A). All 7A and 7A.1 FIAR’s will have interims.

STS-104 (7A) FIAR’s were statused as follows:

JSCEC0839 — REBA Charger. REBA failed to show green LED during acceptance testing.

EC5/ Hiep Nguyen will be going to the contractor (Summit) 5/4/01.

JSCEC0863F — Modular Gimbal Assy. End effector is sticking/not closing (STS-98 anomaly).

EC5/Roger Schwarz reported that he is getting more information from Oceaneering. There may be a "broke" in configuration control. Getting story.

BFCE026A024 — High Strength Bridge Clamp. Unlock push button will not extend.

EC5/Roger Schwarz reported the hardware is going through vibe testing this week.

STS-105 (7A.1) FIAR’s were statused as follows:

BFCE029F105 — Pistol Grip Tool (PGT). PGT Chatter.

EC5/Roger Schwarz reported this FIAR is still unexplained. The PGT will be shipped for MPLM Bench Review the end of the month. Interims will be written within the next 2 weeks. Hardware is to be left on-orbit.

The Chairman requested a note be added to the status to show dates interims are needed, shipping on open DR, etc.

The oldest FIAR, against the Adaptive Payload Carrier, is 589 631 days old.

  1. Certification Status NS22/Greg Wright

There are three hardware certification items open for STS-104 (7A). Certification for the Draeger tube, Contamination Detector Kit, and Gold Salt Hydrazine Detector Kit is expected to be complete 6/7/01. There are two open hardware certifications for STS-105 (7A.1). The EVA Winch and Mount Assemblies will go to the Safety Review Board next week. A GCAR will be routed for signature. There is no open certification for STS-108.

  1. EMU RDR and Certification Status NC512/Jose Fuentes

EMU RDR’s open by flight are as follows:


STS-104 (7A) 0


STS-105 (7A.1) 8


STS-108 (UF1) 18

Final closure is in work for most issues.

There are three open certification items for STS-104 (7A), most require simple paperwork to close. The EMU Middeck Battery Charger is scheduled for the 5/31/01 SMART. Bandages and Dermabond open certification will be part of the same EMUM, which was released by HSWL 5/29/01. There is one open certification item for STS-105 (7A.1). EMU Comfort Gloves cert is pending an ESEL revision to revise the dash number. There is no open certification to report for STS-108 (UF1).



  1. On-Orbit Limited Life Status — NA/Rod TolerRod Toler

The On-Orbit Limited Life Status is to be presented the 2nd and 4th Wednesday of the monthis scheduled for presentation on the 2nd and 4th Wednesday..


  1. USA Limited Life Status — USA/Nancy Jeanne Neason


  2. The USA Limited Life Status is scheduled for presentation on the 2nd and 4th Wednesday.

  3. Funds Transfer Status XA/Janice Hall

Funds transferred this reporting period are as follows:

EMU Protective Visor Coating (6 visors) $66KH-0935R1 - BMRRM Vice Clamp Tool - $52,000


H-0904R2 - QD Bail Drive Levers - 39,000


H-0992 - ISS Truss Element Verification Template - 15,000


H-0988 - QD Female Interlock Defeat (FID) Gauge - 15,000


H-0978 - New EVA Aid for ESO-2 on ULF1 WIF Est - 15,000


H-0986 - Change MMWS Bayonet Receptacles - 99,000


H-0958R1 - QD Demate Tool (Soft Dock Release) - 60,000

EC5/Mike Lawson reported that only partial funding has been received for the CETA Cart and TERA activities. XA/Greg LeStourgeon reported that the entire amount from ISS ($600K) may not have been received. This will be reviewed with the Business Management Office.

  1. IFA Status — XA/Brian JohnsonGlenn Lutz
  2. No IFA status was presented.IFA’s were reviewed and actionees requested to contact XA/Glenn Lutz on status updates/closures.

  3. EMU Rotation Plan (H7130) HSWL/Donna Ray


Revision 2 to the EMU Rotation Plan (H7130) was presented. This revision updates launch dates and sequence according to the FAWG dated 5/10/01.

Decision: Approve.

  1. USA SAFER Flight Logistics Plan (H-0933) — XA/Anh Huynh
  2. Revision 3 to the USA SAFER Flight Logistics Plan was approved OSB on 5/24/01. This revision adds STS-113 (ULF1), and substitutes S/N 1007 for S/N 1003 on STS-105, 11A, and UF4 and S/N 1003 for S/N 1007 on STS-108, 12A, and 10A.

  3. EHB Action Status — XA/Brian JohnsonGlenn Lutz

EHB actions were reviewed and statused as follows:

Action 1/31/01-1: Work issues of shortage of Biomed hardware and bring a CR forward to the EHB.


Per MV5/Bobby Watkins, a meeting will be held today to discuss this issue. Results will be reported to XA/Glenn Lutz.


Action 12/5/00-2: Assess all tools used in SSA [processing or possible inclusion in SSA Maintenance Manual.

XA/Glenn Lutz will discuss off-line with the actionee.

Action 4/30/01-1: Track and report completion of validation testing of the EMU and PWR water storage capability to the 25 EVA levels.

Should meet due date of 6/27/01.

Action 4/25/01-1: Work with MOD to update procedures for HSBC on-orbit unit. Put restrictions on S/N 1004’s use with coordinated comments (caveats) from XA Hardware Group and EC5.

XA/Kristin O’Brien gave constraints to actionee. Action still in work.

Action 12/13/00-2: Work with MOD to understand IRCO2 sensor.

Actionee will be requested to provide date findings will be ready to present to EHB.

Action 2/7/01-1: Change FEMU-R-001 to disallow reuse of CCC’s and to utilize regenerated Metox canisters.

Actionee will be requested to provide date FEMU-R-001 updates are ready to present to EHB.

  1. H-0999 — STS-104 (7A) Open Tool-to-Tool Fitchecks — HSMS/Jeff Case

This CCBD requests EHB concurrence on accepting the risk of not performing all tool-to-tool fitchecks for STS-104. Root cause of the inability to complete the fitchecks is attributed to late addition of tools to the flight and hardware logistics disconnects and repairs. The EVA community agreed that these open fitchecks are low risk. A total of 55 fitchecks remain open for STS-104.

Decision: Approve.

  1. Safety Tether Materials Findings — EC5/Lucie JohannesH7069 — EMU Electrical Harness (EEH) Life Extension Waiver — HSWL/David Brose

This CCBD requests waiving the useful life of I-440 EEH S/N’s 1057, 1059, 1061, 1062 and 1063. This recommendation is based on actual cycles vs. the cert cycle model, material acceptability and the addition of a "one time" inspection and performance test per YTN 1273.

Decision: Hold pending update to waiver to include existing HSWL EMUM which captures all details of waiver and receipt of approved YTN.





No further items were brought forward, and the EHB adjourned.

Submitted by: Approved by:

(Original signed by) (Original signed by)



___________________________ ____________________________


Harriett Attaway Brian Johnson Glenn C. Lutz


EHB Secretary Acting EHB Chairman