EVA Hardware Board (EHB) Minutes of Meeting 28 Mar 2001
The EHB met at JSC on March 28, 2001, in Building 1, Room 360, at 1:00 p.m. Representatives from the following organizations participated:
EVA Project Office
Hardware Development
Integration and Operations
Astronaut Office
Engineering Directorate
Crew & Thermal Systems Division
EVA and Spacesuit Systems
EVA, Robotics, & Crew Systems
SR&QA
FCE/EVA
Hamilton Sundstrand Windsor Locks (HSWL) via telecon
Hamilton Sundstrand Management Services
USA
Lockheed
EHB Board members from the following organizations participated:
XA/Tools and Crew Aids, XA/EMU, XA/Integration and Operations, CB/Astronaut Office, DX3/EVA, Robotics, & Crew Systems, EA/Engineering, EC5/EVA GFE, MV5/FCE, and NA/SR&QA.
The following items were presented:
- Hardware Integration Schedule XA/Barbara Counts
Changes to the schedule were minor and include the STS-105 MPLM KSC Delta Bench Review ship 4/30/01 and MPLM KSC Delta Bench Review 5/15/01.
- PRACA Status NS43/Terry Miller
Sixteen FIARs are open for EVA hardware and are shown by flight as follows:
STS-100 (6A) 0
STS-104 (7A) 10
STS-105 (7A.1) 15
One FIAR was reported past due and was statused as follows:
BFC026F005 Disk/Loop Pin Puller Tool Caddy. Broken tether cord.
Doing return to print. Closure written; to be rerouted for signature.
No new FIARs were reported.
No FIARs are open for STS-100.
STS-104 FIARs were statused as follows:
JSCEC0842 Modular MWS Gimbal Assy. Fraying of end effector cord.
Have closure.
JSCEC0849 Safety Tether. Slow retract of tether.
Per C. Nicollier, CB position is to live with the slow retract. A DR will be written on any future failure.
The oldest FIAR, against the Adaptive Payload Carrier, is 568 days old.
- Certification Status NS22/Greg Wright
- On-Orbit Limited Life Status NA/Rod Toler
All hardware certification is closed for STS-100. There are 20 hardware certification items open for STS-104 and four open hardware certifications for STS-105.
The Bi-Weekly On-Orbit Limited Life Status was presented. Items showing "red" are the MUT Tool Carrier and ORU Transfer Device, both expiring May 2001. The database is still on target for a June release.
USA limited life issues need to be addressed and will be discussed off-line.
- EMU RDR and Certification Status NC512/Charles Sager
EMU RDRs open by flight are as follows:
STS-100 (6A) 4
STS-104 (7A) 8
STS-105 (7A.1) 4
STS-100 RDRs: The two glove and two battery RDRs will be presented at the regular Thursday RDR telecon and are planned to be closed at that time.
STS-104 RDRs: These are planned for closure in the scheduled timeframe.
STS-105 RDRs: These are planned for closure in the scheduled timeframe.
There are no open certification items to report for STS-100.
The are 27 open certification items for STS-104 (7A). Most will come off with ESEL revisions. The SSER cert is in work. Joint A/L stowage items cert memo has been received; waiting for GCAR.
There are 15 open certification items for STS-105 (7A.1). This list will be scrubbed; many items should come off next week.
- Funds Transfer Status XA/Janice Hall
No funds were transferred during this reporting period.
- IFA Status XA/Dale Roberts
- EMU Rotation Plan XA/Brian Johnson
IFA actions will be statused at a special EHB on 4/11/01. It was reported that STS-102 IFA actions assigned to EC5/Bill Spenny are in work and official response will be in the form of an EMUM from HSWL.
HSWL requested deferment of changes to the EMU Rotation Plan to the 4/4/01 EHB, which will include crew issues and addition of 3rd EMU to 8A.
- USA SAFER Flight Logistics Plan XA/Anh Huynh
- EHB Action Status XA/D. Roberts
Changes to the USA Safer Flight Logistics Plan were presented. The plan was revised to substitute S/N 1006 for S/N 1003 on STS-100 and to substitute with S/N 1003 accordingly on subsequent flights.
This item was deferred.
- Walk-on: H7144 EMU SSA Phase VI 12V Heater Modification for 6A and 7A HSWL/Charles Russo
- Walk-on: H7149 EMU SSA Discharge REBA for STS-100 HSWL/Charles Russo
This CCBD requests the build of five 12V heater in-line cable voltage regulator assemblies to be delivered to USA by 4/1/01. A Type A TPS will be processed to install the voltage regulator assemblies into the EMU 02 pocket to support flight for STS-100. The contractor will supply an acceptability for use memo as rationale to use the modified 12V heater system for flight to CTSD by 3/29/01 and electrical verification/checkout procedures to USA by 3/27/01.
The following action was assigned:
Action 3/28/01-1: Present a plan for 12V Heater modifications for subsequent flights.
Actionee(s): HSWL/Bob Mumford; HSWL/Donna Ray
Due Date: 4/9/01
Decision: Route for technical concurrence.
This CCBD requests pre-discharge of the REBA to a steady state voltage of less than 12.8V. The contractor will develop duty cycle and crew response times for a night and day pass for STS-100 based on manned and unmanned testing with the Phase VI gloves. Duty cycle will be documented with a Mission Action Request.
Decision: Tabled for further discussion off-line. To be routed for concurrence OSB.
- Walk-on: Bends Treatment Adapter
- H-0972 Provide Top Mounted Handrails to ISS for Node 2 XA/Kristin OBrien
This item will be discussed off-line.
This CCBD requests providing top mounted handrails to ISS for Node 2 to be delivered as follows:
- P/N SEG33106347-821 – 45 by 6/15/01
- P/N SEG33106347-807 – 3 by 6/1/01
These handrails will come out of the ISS Handrail block buy funded by SSCN 2808 and CR H-0740.
Decision: Route for technical concurrence.
- H-0970 Deliver Top Mounted EVA Handrails for Cupola XA/Kristin OBrien
This CCBD requests top mounted handrails for the top of the Cupola dome to be used for crew stabilization as follows:
- P/N SEG33106347-811 5 by August 2001
- P/N SEG33106347-807 1 by August 2001
These handrails will come out of the ISS Handrail block buy funded by SSCN 2808 and CR H-0740.
Decision: Route for technical concurrence.
- H-0973 Provide Handrails to ISS per PQDS Requirements XA/Kristin OBrien
This CCBD requests providing top mounted and custom handrails to ISS per PQDS requirements as follows:
ISS ID | Part Name | Part Number | Flight | Quantity | Deliver By: |
205717 | TOP-MOUNTED HANDRAIL ASSEMBLY | SEG33106347-801 | 14A | 12 | 5/1/2001 |
205705 | TOP-MOUNTED HANDRAIL ASSEMBLY | SEG33106347-809 | 15A | 12 | 5/1/2001 |
205706 | TOP-MOUNTED HANDRAIL ASSEMBLY | SEG33106347-805 | 15A | 4 | 5/1/2001 |
205708 | CUSTOM HANDRAIL ASSEMBLY | SEG33106466-301 | 15A | 4 | 5/1/2001 |
205735 | TOP-MOUNTED HANDRAIL ASSEMBLY | SEG33106347-803 | 15A | 2 | 5/1/2001 |
205736 | TOP-MOUNTED HANDRAIL ASSEMBLY | SEG33106347-807 | 15A | 16 | 5/1/2001 |
These handrails will come out of the ISS Handrail block buy funded by SSCN 2808 and CR H-0740.
Decision: Route for technical concurrence.
This CCBD requests changing the Draeger Tube Nitrogen Dioxide packaging from a green foil laminate pouch to a clear bite size package.
Decision: Route for technical concurrence.
No further items were brought forward, and the EHB meeting adjourned.