Cosmodrome Plesetsk, June 26 (L-4):

Everything went well today, mostly electrical checks on the integrated
launch vehicle. For tomorrow, June 27 the State Commission will perform the
Launch Readiness Review, where each party has to report on readiness of its
systems or potential open issues. After a positive decision of that
commission, LV fuelling will be performed on June 28 and 29.

Everything is still on GO for June 30.