ESMOS STATUS MEETING MINUTES



The ESMOS Status Meeting was conducted by P. Ondrus at 1:00 PM April 2, 2002. The meeting was held in Room N202 in Building 32.

General Comments and Related Discussion:


The Aqua launch is now no earlier than April 26th. Battery testing is still in progress. The fueling of the second stage is the next milestone.

Discussion of ESMOS Top Ten Issues


The Mission System top ten issues were discussed by K. Dolan.


#1 — FY02 budget – SOMO backing out of funding networks, institutional support and technology programs: Will change from FY02 to FY03 as the title of this item. We are shifting forward; looks like we can make it through the fiscal year.

#2 — Readiness of Ground Network to support Aqua: Next GN test is scheduled for April 8th through the 10th.


#3 — NACs: This item can be lowered on the top ten list. One person’s clearance has been deferred; two new people are in the queue. People without an approved NAC can be escorted by a cleared person.



#4 — Getting a contract in place to provide anomaly support from LMMS, SBRS, and L3COM: There is a telecon tomorrow morning. There are still some issues with the Santa Barbara contract.



#5 — End of Mission planning for ERBS and UARS: No changes since last week. There is an effort to get ERBS and UARS funding through the education outreach program.



#6 — USGS has not provided money to cover FY02 Landsat-7 network costs. NASA has not budgeted for this cost: No changes since last week.



#7 — DSMC transition NCC and WOTIS operations are moving to WSC during 2002: We will be attempting a manual test this week with WOTIS and White Sands.



#8 — System vulnerabilities: Completed an internal assessment. Judy Bruner’s team is looking at system vulnerabilities; we will work to close out any items that they identify.



#9 — Aqua Transition: No updates; final transition plans is not due yet.


Old item #6, NCR, was completed and removed from this top ten list.

Comments by K. Dolan and Related Discussion:


All meetings are not listed on the web site calendar.

A UARS yaw maneuver is scheduled.

The Terra inclination #6 maneuver will be rescheduled.

The MPR is scheduled for Friday and the MSR is on Tuesday. Paul needs a couple of slides on EDOS activities for the MSR from Bonnie Seaton. Should highlight the good things that have been happening on EDOS.

MODIS has returned to operations. Working on loading two software patches; should be completed today. Also looking at possible reprogramming the EEPROM as a further fix.

Comments by B. Guit and Related Discussion:


The Delta ORR for UARS is April 4th.

Paul complimented the UARS team on their efforts during the re-engineering effort.

Comments by H. Wong and Related Discussion:


The Aqua FRR is April 22nd and the launch vehicle ORR is April 24th.

Phil and Rick Pickering are meeting on the transition of Aura.

Comments by C. Sigman and Related Discussion:


The IMT system was compromised for the second time. Paul wants to have a meeting with the parties that were involved. This will be a new policy to have these meetings with the people responsible for a system after it is compromised.

Spread sheets showing system vulnerabilities have been generated.

IST policy needs to be approved and implemented as ESMOS Project policy.

Comments by A. Jansen and Related Discussion:


Getting ready for Aqua launch; daily meetings are being held.

We are reviewing the constraints list.

Comments by B. Kozon and Related Discussion:


A Terra drag maneuver is scheduled for April 10th.

Comments by R. Hudson and Related Discussion:


TOMS monthly was held. Normal operations were reported.

Comments by A. Kelly and Related Discussion:


Rick Pickering is now the Aura project manager.

There is an Aura meeting in the Netherlands next week.

Comments by C. Gomez and Related Discussion:


EDOS is supporting the MOSS test. The load test will be supported next week.

Meeting with the new S/W maintenance team that will be assuming EDOS maintenance.

The investigation of the back jumps in time in ASTER data is continuing. A preliminary report is being prepared. Alex and Paul will review the report prior to distribution.

Comments by R. Lonigro and Related Discussion:


There is a Landsat 7 Delta V this afternoon.

Attendees:


Rich Lonigro


Phil Province


Cindi Adams


Guy Cordier


Angie Kelly


Corinne Reed-Miller


Lou Koschmeder


Bill Guit


Lou Kurzmiller


Ken Dolan


Dave Lorenz


Lucia Gayhart


Rick Hudson


Vickie Lopez


Stephanie Nickens


Bob Kozon


Rory Casey


Taylor Hale


Willie Fuller


Warren Case


Carlos Gomez


Bill Guion


Pat Crouse


Jim Elliott


Pat Johnson


Andrew Jansen


Alex Krimchansky


Ed Macie


Esmond Marvray


Paul Ondrus


Clayton Sigman


Hank Wong


Victor Yocco

SpaceRef staff editor.