Status Report

ESA Rosetta Status Report 9 August 2004

By SpaceRef Editor
August 14, 2004
Filed under , ,
ESA Rosetta Status Report 9 August 2004
http://images.spaceref.com/news/rosetta.jpg

Report for week 30 July to 6 August 2004

In the reporting period the spacecraft was monitored daily (with the exception of two passes) to complete the upload and verification of version 7 of the on-board software. Following the monitoring of the previous week the go ahead for finalization of v7 installation was given on 2 August. From now on the Rosetta spacecraft will be fully controlled via the new software.

Final tests carried out in this period were:

1 August

  • Further Navigation Cameras test, including slews with the cameras in tracking mode

  • Redundant RTU Payload Core and the redundant Solar Array Drive electronics

On 2 and 3 August the loaded command files for processors 2 and 3 patching were executed. Memory dumps and comparisons with the ground software images confirmed the correct patching of the redundant processors with the new on-board avionics software v7.

The OSIRIS instrument was activated manually during the New Norcia pass on 4 August, to support data generation and retrieval tests which were carried out on the following day remotely from the PI’s home institute.

The table below shows a chronology of the main activities in the reporting period:











































Mission Day


Date


DOY


Main Activity


151


30/31.07.04

212/213 Skipped pass

152


31.07/01.08.04

213/214 Skipped pass

153


01/02.08.04

214/215 NAVCAM test dump, redundancy switching

154


02/03.08.04

215/216 Patch software v7 on PM2 and PM3

155


03/04.08.04

216/217 Verify v7 patch by memory dumps

156


04/05.08.04

217/218 Monitoring pass, activate OSIRIS

157


05/06.08.04

218/219 Monitoring pass, test OSIRIS data flow, uplink MTL

At the end of the last New Norcia pass in the reporting period (DOY 219) Rosetta was at 73.6 million Km from the Earth. The one-way signal travel time was 4 min 5 sec.

Please note that the next two issues of this report will occur on a bi-weekly basis, that is on 20 August and on 3 September. After that the normal weekly periodicity will re-start.

SpaceRef staff editor.