EMU Panel Minutes 16 August 2000
The EMU Panel convened at 9:30 a.m. on Wednesday, August 16, 2000. Topics of discussion are as follows:
- Flight Readiness Review
- STS-106/2A.2b (S. Anderson – X39311)
- SSER certification closed August 15, 2000.
- PLSS 1018 will receive the third SOP to be processed at USA.
- Crewman Lus arm brace is currently not certified. It was presented to the MV board accompanied by an EMU acceptability for use memo. EMU actions are complete. Certification needs to be coordinated with CB/Lisa Ristow.
- ETA runs are scheduled for August 23 and 24. There may be a requirement for a TRR for the arm brace.
- EVA check-out timeline is in work to support this flight.
- STS-92/3A (R. McDaniel X33787)
- PLSS TMGs with power harnesses installed were delivered to USA.
- CoFR2 is scheduled for September 8, 2000.
- REBA battery certification testing is complete. The GCAR is in the approval loop.
- I-146 waiver (H7075) needs approval for USA to continue processing for this flight. This wavier is scheduled for the EMU Panel and the EHB on August 23.
- STS-97/ 4A (C. Donnellan – X35896)
- This is the first fight of the DIDB (Disposable In-suit Drink Bag) for EMU use.
- At this time there is no waiver required for the EMU Batteries for this flight.
- STS-98/ 5A (D. Oswald X39330)
- STS-102/ 5A.1 (S. Anderson X39311)
No issues to report.
- A draft of the STS-102 ESEL is in work with XA.
- STS-109/HST-3B
- A draft of the STS-109 ESEL is in work with XA.
- The current EVA plan for this flight is five (5) scheduled, one (1) unscheduled, and two (2) contingency EVAs.
II. PLSS and DCM Hardware Status
Deferred
III. RDR/FIAR Status
Deferred
IV. Certification Status
Deferred
V. CCBDs and PPDOs
The following items were presented and directed as follows:
- H7028 EMU LSS Battery Wet-Life Extension Deferred.
- H7065 EMU LSS EEH Wiring and Soldering Deviation Return to EMU Panel.
- H7076 EMU SSA Documentation Update for New Fresnel Lens Return to EMU Panel.
- H6980R1 EMU LSS Incorporation of Alternate SOP Pressure Transducer I-215 Approved with changes.
- H7080 EMU Program 100% Fit Check Requirement for Flight Hardware Return to EMU Panel.
- H7075 EMU LSS Waive Useful Life of Five I-146 Positive Pressure Relief Valves Deferred.
- H7044R1 EMU LSS CWS Redesign Effort Outside of Panel.
- H7072 EMU SSA Standard Repair Procedure for Looptape Base Cloth Windowing. Deferred.
VI. ACTION ITEMS
Deferred
The following actions are open:
00-22 J. Ferketic Review the CM plan regarding the YTN process versus what we are working to. Provide corrective action to improve the process. Present recommendations and findings at the LSS and SSA telecons prior to EMU Panel. Due May 31, 2000. Current process is not acceptable. Evaluate process change and return to EMU Panel. Due June 28, 2000.
00-24 N. Lefferts Provide a schedule for IRCO2 replacements. Due August 9, 2000.
00-25 S. Dionne Present recommendation for improving the Service Instruction process to better include USA/FCE EVA. Due July 19, 2000.
00-26 M. Puskar Provide a plan to re-certify the remaining batteries as risk mitigation to the advanced battery. Due August 16, 2000.
00-27 M. Puskar Provide a plan to update battery certification to 270 days. Due September 6, 2000.
No actions were closed.
No new actions were assigned:
The next action number to be assigned is 00-26.
VII. Issues and Special Topics
DX/C. Yates EMU Equipment Bag – Deferred
Prepared by: Approved by:
(Original signed by) (Original signed by)
Tami R. Ethridge Brian J. Johnson
EMU Configuration EMU Panel Chairman