Chandra Operations CXO Status Report 31 May 2002, 5.00pm EDT
During the last week, Chandra completed the observing schedule as planned.
Preparations are complete for the Jun 2-6 American Astronomical Society (AAS) meeting in Albuquerque, NM, where a Chandra press conference and two press releases are planned.
The observing schedule for the next week is shown below and includes a continuation of the long observation of Sgr A* and an observation of M31 coordinated with the Hubble Space Telescope.
------------------------------------------- M31 ACIS-I Jun 2 Sgr A* ACIS-I 3C273 ACIS-S/LETG Jun 3 Radiation Belts Jun 4 3C273 (3 obs) ACIS-S/HETG NGC 5044 ACIS-S/HETG Jun 5 Radiation Belts Jun 6 NGC 5044 ACIS-S/HETG Jun 7 Quest 1220-0025 ACIS-S Jun 8 M87 ACIS-S NGC 4136 X-1 ACIS-S Field-142549+353248 ACIS-I -------------------------------------------
All spacecraft subsystems continued to operate nominally.