NASA Space Station On-Orbit Status 3 May 2018 - Preparing for the Next Spacewalk.
NASA

The Expedition 55 crew members are getting their U.S. spacesuits and equipment ready for a spacewalk in two weeks. The Dragon cargo craft from SpaceX is nearly loaded with NASA science and gear ahead of its Saturday return to Earth.
NASA astronauts Ricky Arnold and Drew Feustel are assembling hardware today that will be installed on the International Space Station when they conduct a spacewalk on May 16. The duo were assisted throughout the day by fellow NASA astronaut Scott Tingle scrubbing U.S. spacesuit water cooling loops and testing water samples for conductivity.

The veteran spacewalkers were mating repaired components from an external television camera group (ETVCG) that will be attached to the starboard side of the Destiny laboratory module. Their primary spacewalking task however, will be the swap out of thermal control gear that circulates ammonia to keep station systems cool.

Final packing is taking place inside the Dragon space freighter today as Tingle loads critical time-sensitive research samples inside the Earth-bound resupply ship. Robotics controllers will detach Dragon from the Harmony module Friday before releasing it Saturday at 9:24 a.m. from the grips of the Canadarm2. NASA TV will begin its live broadcast of the departure at 9 a.m. but will not televise its 3 p.m. splashdown in the Pacific Ocean.

On-Orbit Status Report

Miniature Exercise Device (MED-2): The MED-2 session planned for today was postponed due to time constraints.

SpaceX-14 Cold Stowage: The crew implemented changes in the cold stowage plan today to support the return of blood samples on the SpX-14 vehicle.

Extravehicular Mobility Unit (EMU) Loop Scrub and Conductivity Test: As part of the preparation activities needed to support the upcoming US EVA Pump Flow Control System (PFCS) Relocate currently planned on May 16th, the crew performed EMU water loop scrubs and tested water samples for conductivity. During the maintenance activities, the crew noted that EMU 3006 was making an unexpected noise. While suit telemetry appeared nominal, and no hardware issues were noted throughout the activities, a recording of the anomalous sound was provided to engineering teams for review.

External TV Camera Group (ETVCG) Assembly: Today the crew completed assembly of an ETVCG for use in the upcoming US EVA on 16-May. This new ETVCG was constructed using the Light Assembly that was recently repaired by the crew on-orbit. Despite multiple attempts, the crew was unable to confirm full engagement of the locking mechanism that holds the External High Definition Camera (EHDC) onto the Color TV Camera (CTVC). Engineering teams are currently reviewing photos and ground test data to determine whether or not additional action is required prior to the EVA.

Zero-Gravity Stowage Rack (ZSR) Photography: In preparation for installation of the Life Sciences Glovebox (LSG) arriving on HTV-7, the crew took specialized photos of the ZSR rack, and surrounding structure, at the JPM1F5 location. Ground specialists will use these photos to verify that on-orbit rack clearances match engineering models using a technique known as Photogrammetry. Fundamentally, photogrammetry is about measurement: the measuring of the imaged object. The process involves taking overlapping photographs of an object and converting them into 2D or 3D digital models. By including objects of known length in the photographs, 3D models can be generated with a known scale. The results of this work will directly affect the verification and development of hardware required to install LSG later this year.

Today’s Planned Activities
All activities are complete unless otherwise noted.

Cargo Transfer from Dragon
Cell Biology Experiment Facility (CBEF) Mouse Habitat Cage Unit Installation for Micro-G and 1G
Extravehicular Mobility Unit (EMU) Cooling Loop Maintenance Scrub Initiation
Correction of lettering on the painted surface of Quick Release Screw Clamps (???) No.3 installed on SM Aft – Progress 438 Interface
PROBOY. Connecting Acoustic Signal Converter Unit (????) cable and activation of ????
TangoLab-1 Card Cube Replace
PROBOY. Software Update.
Cleaning FGB ??1 Circulation Fan Screens
??? maintenance
Vacuum Cleaning ??1 and ??2 air ducts in MRM2
PROFILAKTIKA-2. Preparation for the experiment.
Water Recovery and Management Condensate Pumping Init
PROFILAKTIKA-2.Operator Assistance in Preparation for the Experiment
Portable Fan Assembly Restow and Inspect
In-flight Maintenance (IFM) External Television Camera Group (ETVCG) Gather
Water Recovery and Management Condensate Pumping Term
PROFILAKTIKA-2. Experiment Ops on ??-2 Treadmill (Individual strategy test).
Extravehicular Mobility Unit (EMU) Post Scrub Cooling Loop Water (H2O) Sample
PROFILAKTIKA-2.Closeout Ops.
External Television Camera Group Assist
External Television Camera Group (ETVCG) Assemble
EVA Extravehicular Mobility Unit (EMU) Cooling Loop Scrub Deconfiguration
Preventive Maintenance of FS1 Laptop
ZSR Rack Front Stowage Relocate
BRI Monthly Maintenance Note 6
PROFILAKTIKA-2. Hygiene Procedures
High Definition Video Camera Assemby 2 Activation in High Definition Mode [Aborted]
External Television Camera Group (ETVCG) Light Bulb R&R and Assembly Restow
Probiotics Item Gathering
???? Reconfiguration in MRM1
PWS1 booting in safe mode [Aborted]
SEPARATION. ???-? replacement.
SEPARATION. Activation of the 4th distillation.
IMS Update
HDVCA2 SD setting and PWS1 power off post PWS1 Troubleshooting [Aborted]
Miniature Exercise Device Operations Session
ZSR and JPM1F5 Photos
CONTENT. Experiment Ops
SEPARATION.
Environmental Health System (EHS) – Rad Detector Relocate
PROBOY. RS?1 Laptop Ops.
PROBOY. Penetration Simulator Ops.
Extravehicular Mobility Unit (EMU) Conductivity Test
ISS HAM Service Module Pass
SEPARATION. Log-file downlink
SEPARATION. Replacement and ???-? Water Sample Collection.
???? reconfiguration in MRM1
PROBOY. Copy and Downlink Data
ISS HAM Service Module Pass
HRF ZBook Retrieve
Symbolic Activity (Setup)
TangoLab-1 Card Cube Remove
Cargo transfer to Dragon
ZSR and JPM1F5 Photos Part 3
ZSR Photos Restow
Stow Syringes used in H2O Conductivity Test

Completed Task List Activities
None

Ground Activities
All activities are complete unless otherwise noted.
Battery 3B2 Capacity Test
SPDM Direct Drive Testing

Three-Day Look Ahead:
Friday, 05/04: Dragon Double Cold Bag Repack, Dragon Center Stack Transfer, Dragon Egress and Closeout
Saturday, 05/05: Housekeeping, Dragon Release Operations
Sunday, 05/06: Crew Off-Duty

QUICK ISS Status – Environmental Control Group:
Component – Status
Elektron – On
Vozdukh – Manual
[???] 1 – SM Air Conditioner System (“SKV1”) – Off
[???] 2 – SM Air Conditioner System (“SKV2”) – On
Carbon Dioxide Removal Assembly (CDRA) Lab – Operate
Carbon Dioxide Removal Assembly (CDRA) Node 3 – Standby
Major Constituent Analyzer (MCA) Lab – Operate
Major Constituent Analyzer (MCA) Node 3 – Idle
Oxygen Generation Assembly (OGA) – Process
Urine Processing Assembly (UPA) – Standby
Trace Contaminant Control System (TCCS) Lab – Full Up
Trace Contaminant Control System (TCCS) Node 3 – Off