NASA ISS On-Orbit Status 12 January 2014
Today: Mobile Servicing System (MSS) Operations for Cygnus Capture: Today the Robotics Ground Controllers powered up the MSS and performed a Node-2 Nadir Active Common Berthing Mechanism (CBM) survey with the Space Station Remote Manipulator System (SSRMS).
They then maneuvered the SSRMS to the Cygnus High Hover position in preparation for capture and powered the MSS into the hot backup configuration.
Flight Engineer (FE)-5 Mastracchio and FE-6 Wakata monitored the Cygnus approach from the Cupola Robotic Workstation (RWS) and captured Cygnus using the SSRMS at approximately 5:08am CST. They then maneuvered Cygnus into position to inspect the Passive CBM and proceeded with a successful installation onto the Node-2 Nadir Active CBM. The crew was ahead of the timeline today and continued with Controller Panel Assembly (CPA) removal, hatch opening/ingress, and started cargo transfer which were all originally scheduled for Monday, January 13th.
Today’s Planned Tasks
PROK – Urine Collection Ops [Complete]
HRF – Blood Collection [Complete]
USOS Window Shutter Close [Complete]
HRF- Centrifuge Configure [Complete]
HRF- remove blood tubes and power off Centrifuge [Complete]
HRF- Sample MELFI Insertion [Complete]
HRF- Closeout Ops [Complete]
CBCS Powerup [Complete]
Configure RWS for monitoring Cygnus approach [Complete]
Cygnus – PCS Command and PROX Link Verification [Complete]
HHL Setup for Cygnus capture [Complete]
LAB Camcorder setup at LAB RWS Mon 3 for Downlink [Complete]
Cygnus R-BAR Approach [Complete]
KAPLYA-2. Start SONY Battery Charging [Complete]
SSRMS Cygnus Capture [Complete]
SSRMS – Maneuver Cygnus to the PCBM inspection position [Complete]
CYGNUS PCBM Inspect [Complete]
HRF – Urine Collection Ops [Complete]
Verify Node 2 Nadir CBM Pre-mate Status [Complete]
Maneuver Cygnus to ready-to-latch position using SSRMS [Complete]
HRF- insert samples to MELFI [Complete]
Node 2 CBM – Capture and Abolts [Complete]
SSRMS – Cygnus Installation Limp [Complete]
SSRMS – Cygnus Installation Brake [Complete]
CBCS – Camera Remove [Complete]
HRF – Urine Collection Ops [Complete]
??? Maintenance. SM and FGB ???, ???, ??? ???? Counter, POTOK Air Purification System Data Calldowns [Complete]
HRF- insert samples to MELFI [Complete]
ANTS- Procedure Review [Complete]
Cygnus/Node 2 – Pressurization and leak check [Complete]
KAPLYA -2. Terminate SONY Battery Charging and Set up Next Battery for Charging [Complete]
Hardware Command Panel (HCP) Temp Stow [Complete]
Cygnus – Cargo Prep [Complete]
PROK – capture photos of Diet Logfile and pH Logsheet [Complete]
Node 2 Nadir – Cygnus Outfitting Part 1 [Complete]
Hand Held LIDAR (HHL) Adjustments for Cygnus Capture [Complete]
Removal of Mini-Camera and AVIU from Node3/Cupola [Complete]
RWS. Video Downlink End [Complete]
ANTS – Procedure Review [Complete]
Cygnus PROX Switch OFF [Complete]
HRF- Stow hardware used during urine collection ops [Complete]
TERMO-LADA. Visual Inspection of Hardware Operation [Complete]
KAPLYA-2. Terminate SONY Battery Charging [Complete]
Cupola Window Shutter Close [Complete]
Task List
ARED Cylinder Evac
???-? R&R
Preparation of reports for Roskosmos site
SEINER. World Ocean Observation
EKON-M. Observations and photography
Deploy AC INVERTER on LAB UOP2-J4, PS-120 Junction Box J4
ENERGY Equipment Pre-gather
National Geographic B Roll Part 4 [In Work]
Cable Consolidation
Columbus HD Assessment
Fluid Plug Gather
Audit and consolidate wet trash bags and trash bag liners.
Transfer Cygnus Cargo Operations
Ground
Nominal Commanding [Complete]
Three-Day Look Ahead:
Monday, 01/13: Cargo Ops, Ants In Space
Tuesday, 01/14: Emergency egress drill, Cargo Ops, SPHERES
Wednesday, 01/15: Emergency OBT, Try Zero G Exp, SPHERES, Sabatier Purges
QUICK ISS Status – Environmental Control Group:
Component – Status
Elektron – On
Vozdukh – Manual
[???] 1 – SM Air Conditioner System (“SKV1”) – On
[???] 2 – SM Air Conditioner System (“SKV2”) – Off
Carbon Dioxide Removal Assembly (CDRA) Lab – Standby
Carbon Dioxide Removal Assembly (CDRA) Node 3 – Operate
Major Constituent Analyzer (MCA) Lab – Off
Major Constituent Analyzer (MCA) Node 3 – Operate
Oxygen Generation Assembly (OGA) – Process
Urine Processing Assembly (UPA) – Standby
Trace Contaminant Control System (TCCS) Lab – Off
Trace Contaminant Control System (TCCS) Node 3 – Full up