DMSP

OPS48 rev 29296 R+03 / F at 0611z on December 8:  A CAT 3 data loss was declared due to a problem with the bit sync at Fairbanks (1438 spacecraft seconds, 39.95 playback seconds)

DMSP operations were nominal over the past 72 hours.

POES
 

POES operations were nominal over the past 72 hours.

GOES

At 1356z on December 6, a GOES-10 frame break was observed and attributed to loss of signal synchronization.

At 0350z on December 7, a GOES-8 frame break was observed and attributed to an errant switch setting during a ground loop calibration.

At 1256z on December 8, a GOES-10 frame break was observed and attributed to loss of signal synchronization.

Note:  The GOES-8 to GOES-12 Transition plan for the GOES-East mission can be retrieved via http://www.oso.noaa.gov/goes/index.htm.

GOES operations were nominal over the past 72 hours.