Status Report

Space Shuttle Processing Status 10 Sep 2002

By SpaceRef Editor
September 10, 2002
Filed under , ,

MISSION STS-112 — 15TH ISS FLIGHT (9A) – S1 Truss Segment

VEHICLE: Atlantis/OV-104

TARGET LAUNCH DATE: Oct. 2, 2002 NET

TARGET LAUNCH PERIOD: 2 – 6 p.m. EDT

TARGET LANDING DATE: Oct. 13, 2002

MISSION DURATION: 11 days

CREW: Ashby, Melroy, Wolf, Sellers, Magnus, Yurchikhin

ORBITAL ALTITUDE AND INCLINATION: 122 nautical miles, 51.6 degrees

Shuttle Processing Note: After being stacked with its Solid Rocket Boosters and External Tank, Atlantis began its roll out to Pad 39B this morning at 2:27 a.m. in preparation for launch to the International Space Station. The Shuttle arrived at the Pad and was hard down at 9:38 a.m. After technicians noted a concern in the mid-body regarding movement of the Manipulator Positioning Mechanism that is attached to the Remote Manipulator System in the payload bay, engineers determined that additional work can be performed while the vehicle is at the pad.

Crawler Transporter No. 2 retests with the Mobile Launcher Platform were successfully completed after technicians replaced bearings located in the JEL (jacking, equalization and leveling) cylinders. The repaired cylinders on the crawler performed flawlessly during Atlantis’ roll to the Pad.

MISSION: STS-113 – 16th ISS Flight (11A) – P1 Truss Segment

VEHICLE: Endeavour/OV-105

TARGET LAUNCH DATE: Nov. 2, 2002 NET

TARGET LANDING DATE: Nov. 13, 2002

MISSION DURATION: 11 days

CREW: Wetherbee, Lockhart, Lopez-Alegria, Herrington; (ISS up) Bowersox, Budarin, Pettit; (ISS down) Korzun, Whitson, Treschev

ORBITAL INSERTION ALTITUDE AND INCLINATION: 122 nautical miles/51.6 degrees

Shuttle Processing Note: Endeavour’s aft closeouts continue in preparation for its upcoming launch to the International Space Station. Forward compartment closeouts begin today. The crew participated in the Crew Equipment Interface Test (CEIT) over the weekend.

MISSION STS-107 -SPACEHAB/ FREESTAR MICROGRAVITY RESEARCH MISSION

VEHICLE – Columbia/OV-102

TARGET LAUNCH DATE: Jan. 16, 2003 NET

TARGET LANDING DATE: Feb. 1, 2003

MISSION DURATION: 16 days

CREW: Husband, McCool, Anderson, Chawla, Brown, Clark, Ramon

ORBITAL INSERTION ALTITUDE AND INCLINATION: 150 nautical miles/39 degrees

Shuttle Processing Note: Nominal processing has been completed in preparation for Columbia’s research mission now scheduled for no earlier than Jan. 16.

ORBITER MAJOR MODIFICATION PERIOD

VEHICLE: Discovery/OV-103

Shuttle Processing Note: The Orbiter Major Modification (OMM) period for Discovery is underway with radiator removal and nose landing gear retraction. Wire inspections continue and will be performed throughout the entire vehicle during the OMM.

SpaceRef staff editor.