GOES Weekly Operations Plan: 14-20 Jan 2002
1. EAST SPACECRAFT (GOES-8)A. CONTINUOUS IMAGE OPERATIONS AT 15 & 45 MINS PAST EACH HOUR AND
CONTINUOUS SOUNDER OPERATIONS AT 20 & 46 MINS PAST EACH HOUR
WITH THE FOLLOWING EXCEPTIONS:
1) HOUSEKEEPING PERIODS AT 0030Z, 1234Z, & 1834Z.
2) IMAGES CANCELED DUE TO SINGLE CHORD OPERATIONS:
NONE.B. SEM: ON; CALIBRATION EACH WEDNESDAY AT 1834Z.
C. EAST WEFAX AND EMWIN BROADCASTS: CONTINUOUS.
D. EAST DCS: DCPR & DCPI.
E. MANEUVER: NONE.
2. WEST SPACECRAFT (GOES-10)
A. CONTINUOUS IMAGE OPERATIONS AT 00 & 30 MINS PAST EACH HOUR AND
CONTINUOUS SOUNDER OPERATIONS AT 01 & 24 MINS PAST EACH HOUR
WITH THE FOLLOWING EXCEPTIONS:
1) HOUSEKEEPING PERIODS AT 0346Z, 1550Z AND 2145Z.
2) IMAGES CANCELED DUE TO SINGLE CHORD OPERATIONS:
18 JAN – 1452Z.B. SEM: ON; CALIBRATION EACH THURSDAY AT 2151Z.
C. WEST WEFAX AND EMWIN BROADCASTS: CONTINUOUS.
D. WEST DCS: DCPR & DCPI.
E. MANEUVER:NONE.
3. STANDBY SPACECRAFT (GOES-9)
A. NORMAL ORBIT MODE TESTING THROUGH JAN 16. BACK TO STORAGE MODE
JAN 17.B. MANEUVER: NONE.
4. STANDBY SPACECRAFT (GOES-11)
A. STORAGE MODE.
B. MANEUVER NONE.
5. STANDBY SPACECRAFT (GOES-12)
A. STORAGE MODE.
B. MANEUVER NONE.
6. STANDBY SPACECRAFT (GOES-7)
A. MANEUVER: NONE.